联邦政府披露更多关于特朗普政府要求推迟戈迪·豪大桥开通的细节Feds disclose more details on Trump admin request to delay Gordie Howe bridge opening

点「原文对照」整页切到原文,或双击某段只看那段的原文。

加拿大政府披露了关于戈迪·豪国际大桥开通延误的少量新细节,以及一些与建设这座连接安大略省和密歇根州的大型跨境大桥成本相关的信息。

The Canadian government has disclosed a handful of fresh details around the delays in opening the Gordie Howe International Bridge as well as some information related to the cost to build the sprawling span connecting Ontario and Michigan.

但触发此次披露的国会议员表示,他对这些回应“完全不满意”,指责渥太华仍在隐瞒关于这座耗资64亿加元大桥的关键信息,该大桥今年早些时候陷入了跨境政治争议。

But the MP whose questions triggered the disclosure says he’s “not satisfied at all” with the responses, accusing Ottawa of still hiding key information about the $6.4-billion bridge that became mired in cross-border political controversy earlier this year.

温莎西选区保守党国会议员哈布·吉尔表示:“真相最终会大白,越是遮遮掩掩,越会让人起疑。”特别是联邦当局拒绝提供关于开通大桥所需额外成本的详细信息。

"The truth is going to come out eventually, and the more you beat around the bush, the more suspicious people get," says Harb Gill, the Conservative MP for Windsor West. In particular, federal authorities declined to provide details about some of the extra costs to get the bridge open.

尽管如此,部分回应仍为这个被卷入更广泛跨境紧张局势的重大基础设施项目提供了更多线索。今年2月,美国总统唐纳德·特朗普曾威胁阻止该大桥开通。

Still, some of the responses shed additional light on a major infrastructure project that was swept up in broader cross-border tensions when U.S. President Donald Trump threatened to block the bridge’s opening in February. That threat followed intense lobbying and hefty donations to Republicans from the owners of the nearby Ambassador Bridge.

这一威胁是在附近大使桥业主向共和党进行密集游说并作出巨额捐款之后发生的。

Morouns ramped up bridge lobbying before Trump’s Gordie Howe threats Exclusive Ambassador Bridge 'aggressively' pursued trucking clients amid Gordie Howe delay: industry rep In June, Prime Minister Mark Carney said the U.S.

在特朗普威胁戈迪·豪大桥前,莫伦家族加大了大桥游说力度 独家:业内人士称大使桥在戈迪·豪大桥延误期间“激进”争夺货运客户 6月,总理马克·卡尼表示美国……曾要求推迟新大桥开通,理由是提出了“技术方面”的问题。当时他拒绝解释这些技术问题,称:“我不认为在公开场合处理这些问题有成效。”

had requested to delay opening the new bridge, citing “technical aspects” that had been raised. He declined to explain those technical issues at the time, saying, “I don’t think it’s productive to work through those in public.”

本周早些时候,联邦政府回复了吉尔6月份的提问,称美国的请求是在“6月10日前后”提出的,那些技术问题“与大桥相关的治理和财务框架有关”。根据住房、基础设施和社区部的回复,同一天,基础设施部、枢密院、总理办公室和加拿大环球事务部的高级政府官员和部长幕僚“共同接受了简报”,内容是关于美国要求推迟开通大桥的请求。

Earlier this week, the federal government responded to Gill's questions from June, saying that the request from the U.S. came “on or about” June 10, and that those technical issues were “related to the governance and financial framework associated with the bridge." That same day, top government officials and ministerial staff from the infrastructure department, Privy Council Office, Prime Minister’s Office, and Global Affairs Canada “were collectively briefed” on the U.S. request to push back the opening, per the response from Housing, Infrastructure and Communities Canada.

对这些问题的描述似乎与两国最终达成的于7月底开通大桥的协议条款相符。该协议引入了与美国的收益分享安排以及通行费费率变更规则等内容。

The description of the issues appears to track with the provisions of the eventual deal between the two countries to open the bridge in late July. The agreement introduced a revenue-sharing arrangement with the U.S. and rules around toll rate changes, among other things.

总理本应更坦诚:议员吉尔表示,卡尼6月份对这些问题的解释具有误导性,因为“技术”一词暗示“大桥本身在技术上出了问题”。

PM needed to be more forthcoming: MP Gill says Carney’s explanation of the issues in June was misleading, however, because the word “technical” implied “something that was technically wrong with the bridge” itself.

吉尔本周表示:“显然,这根本不是技术问题。而是治理和财务框架问题。如果是这样,那就直说。为什么要躲在‘这是技术问题’这种说辞后面?”截至发稿前,总理办公室和基础设施部均未回复置评请求。白宫也未作出回应。

“Obviously, it was nothing technical,” Gill said this week. “It was the governance and financial framework. So if that's the case, then just say so. Why hide behind these other lines of ‘it's a technical issue’?”Neither the Prime Minister’s Office nor the infrastructure department responded to questions before publication time.

根据对吉尔提问的回复,一系列政府机构参与了“识别、评估或解决”导致6月份推迟的悬而未决的问题:基础设施部;温莎-底特律大桥管理局(运营新大桥的联邦皇家公司);枢密院办公室;加拿大环球事务部;密歇根州交通部;以及两国的边境机构和大使馆。

The White House also did not respond.

不过,这并非大桥通车前的唯一延误。在对吉尔提问的单独回复中,大桥管理局表示,其与“联合北美”财团(负责设计和建设新大桥的私营企业联盟)签署的原始合同“规定了2024年11月的实质性完工日期”。

According to the responses to Gill's questions, though, a wide range of government entities were involved in “identifying, assessing, or addressing” the outstanding issues that led to the June delay: the infrastructure department; the Windsor Detroit Bridge Authority, the Crown corporation that runs the new bridge; Privy Council Office; Global Affairs Canada; Michigan’s Department of Transportation; and both countries’ border agencies and embassies. That wasn’t the only delay in getting the bridge across the finish line, though.

但到了那一年的1月,协议经过修订,将截止日期定为2025年9月,“通车时间定于2025年秋季”。

In separate responses to Gill's questions, the WDBA said its original contract with Bridging North America, the consortium of private firms tasked with designing and building the new span, "set out a substantial completion date of November 2024."

通车时间又在2025年10月再次推迟,当时大桥管理局“表示大桥将于2026年初尽快通车,随后又定为2026年春季的目标时间表”。大桥最终于2026年7月27日通车。

But in January of that year, the deal was amended to make September 2025 the deadline, "with the opening occurring in fall 2025." The opening was pushed back again in October 2025, when the WDBA “stated that the bridge would open as soon as early 2026, and later to the targeted timeline of spring 2026.”

戈迪·豪大桥通车首月车流量超34万 “影响交付时间表的因素包括COVID-19全球大流行造成的前所未有的干扰、作为强有力质量管理一部分的测试和调试,以及部分施工活动,”大桥管理局在对吉尔提问的回复中写道。

The bridge eventually opened on July 27, 2026.

核算成本 基础设施部表示,美方在春季提出的通车延期要求并未增加大桥的价格标签。

Gordie Howe bridge vehicle traffic tops 340,000 in first full month of operation "Factors contributing to delivery timelines included unprecedented disruptions as a result of the COVID-19 global pandemic, testing and commissioning as part of strong quality management, and some construction activities," the bridge authority wrote in response to Gill’s questions.

然而,项目成本已从2018年的57亿加元增至2024年的64亿加元。吉尔表示,他曾向政府询问建设合同变更令的价值,以便详细核算这7亿加元的差额。

Calculating the costs The opening delay requested by the U.S. in the spring did not increase the bridge’s price tag, the infrastructure department wrote. The project costs had jumped from $5.7 billion in 2018 to $6.4 billion in 2024, however.

联邦当局表示:戈迪·豪大桥造价虽有延误但仍为64亿美元,温莎-底特律大桥管理局未在对吉尔的回复中给出答案。

Gill says he asked the government for the value of change orders to the construction contract in order to get a detailed accounting of the $700 million difference.

管理局写道:“温莎-底特律大桥管理局经评估认为,要对这个问题做出全面且经过验证的答复,需要进行人工信息收集,这在规定时间内无法完成,并可能导致披露不完整和误导性的信息。”吉尔则认为,如果价格上涨是由于疫情引起的,“他们应该能告诉我们这7亿美元究竟花在了哪里。这可不是一笔小钱。”周四,温莎-底特律大桥管理局首席关系官希瑟·格朗丁在书面声明中表示,该管理局“一直本着透明的原则并根据政府要求分享信息”。

Gordie Howe bridge cost still $6.4B despite delays, federal authority says But the WDBA didn’t provide answers in their response to Gill. “Windsor-Detroit Bridge Authority has concluded that producing and validating a comprehensive response to this question would require a manual collection of information that is not possible in the time allotted and could lead to the disclosure of incomplete and misleading information," the authority wrote Gill argues that if the price jump was due to the pandemic, “they should be able to tell us exactly where the $700 million went. That's not chump change.”In a written statement Thursday, Heather Grondin, the WDBA's chief relations officer, said the authority "shares information transparently and in accordance with government requirements.

“提供给吉尔议员的回复反映了现有信息,我们将直接与该议员合作,进一步了解他的关切。”吉尔表示,他将继续在下议院以及通过其在该院工业委员会的成员身份,为获取更详尽的答复而不懈努力。

"The responses provided to MP Gill reflect available information and we will work directly with the MP to further understand his concerns." Gill says he’ll keep pursuing more fulsome answers to his questions, both in the House of Commons and through his membership on the chamber’s industry committee.