检查并不等同于改进美国联邦航空管理局的计划A check is not a plan for improving the FAA

点「原文对照」整页切到原文,或双击某段只看那段的原文。

美国联邦航空管理局局长布莱恩·贝德福德于2025年12月16日星期二在华盛顿国会山举行的众议院交通与基础设施委员会航空小组委员会听证会上发言。(美联社照片/马克·希费尔拜因)FAA Administrator Bryan Bedford speaks during a hearing of the Aviation Subcommittee of the House Transportation and Infrastructure Committee on Capitol Hill, Tuesday, Dec. 16, 2025, in Washington. (AP Photo/Mark Schiefelbein)

9月21日,美国联邦航空管理局(FAA)费城进近管制区(TRACON)的一条老化电路发生故障。系统切换至备用系统时,发现光纤已被切断。原来是新 Jersey 州的一个施工队将其挖断了。东北部的五个主要机场随即实施了地面停飞:纽瓦克、特特罗伯罗、费城、拉瓜迪亚和肯尼迪机场。

On Sept. 21, an aging circuit feeding the FAA’s Philadelphia approach control, or TRACON, failed. The system switched to its backup and found the fiber cut. A construction crew in New Jersey had dug it up. Five major Northeast airports went into ground stops: Newark, Teterboro, Philadelphia, LaGuardia and Kennedy.

杰克逊·谢德尔鲍尔(Jackson Shedelbower)在10月1日的专栏文章中,将那一天称为又一次“提醒”,说明国会为何应批准交通部长肖恩·达菲(Sean Duffy)提出的300亿美元拨款请求。我曾在FAA从事了23年的空中交通管制工作,担任过管制员、质量保证与培训专家、一线经理以及空中交通经理。没有人比那些在这个系统工作过的人更希望这个系统实现现代化。但他的论点却把教训完全弄反了。

In an Oct. 1 op-ed, Jackson Shedelbower called that day “another reminder” of why Congress should grant Transportation Secretary Sean Duffy’s $30 billion request. I spent 23 years in FAA air traffic control as a controller, quality assurance and training specialist, front-line manager and air traffic manager. Nobody wants this system modernized more than the people who have worked it. But his argument reads the lesson backward.

先从他正确的地方说起。设备确实很老旧。发生故障的那条电路原本就计划进行更换。管制员和技术人员凭借高超的技能和顽强的精神维持着这个系统的运行,他们理应获得更好的工具。国会应当为此买单。管制员工会支持这项拨款请求,航空公司和飞行员也同样支持。

Start with what he gets right. The equipment is old. The circuit that failed was slated for replacement. Controllers and technicians keep this system running with skill and stubbornness, and they deserve better tools. Congress should pay for them. The controllers’ union backs the request, and so do the airlines and the pilots.

再看他自己提供的证据。他报道称,大约三分之二的老旧铜缆已被替换为光纤或无线链路。然而系统崩溃还是发生了,施工队切断的那条线路恰恰就是光纤。挖掘机可不在乎它切断的电缆是铜制的还是玻璃制的。

Now his own evidence. He reports that roughly two-thirds of the old copper has been replaced with fiber or wireless links. The meltdown happened anyway, and the line the crew cut was fiber. A backhoe does not care whether the cable it cuts is copper or glass.

他还提到了这笔新资金将用于购买什么:“现代化的空中交通流量管理系统和人工智能驱动的软件。”这两者都不是通往管制设施的第二条路线。

He also says what the next money buys: “a modern air traffic flow management system and AI-powered software.”Neither is a second route into a control facility.

FAA局长布赖恩·贝德福德(Bryan Bedford)当天也说了类似的话。他说,该机构正在铺设光纤,但这是“我们使用了50年的相同数据架构”。他希望获得资金来更换它。然而,FAA的负责人却在告诉你们,问题出在设计上。

FAA Administrator Bryan Bedford said as much that day. The agency is laying fiber, he said, but it is “the same data architecture that we’ve had for 50 years.”He wants money to replace it. But the head of the FAA is telling you the problem is design.

韧性来自于独立的物理路线、在负载下经过测试的备份系统,以及当某个部件失效时能够平稳降级的系统。资金可以买到这些,但资金本身创造不出这些。

Resilience comes from separate physical routes, backups that are tested under load and systems that degrade gracefully when a piece drops out. Money pays for them. Money does not make them.

我们已经进行过这项实验。2025年春季纽瓦克停电后,联邦航空局在纽约和费城之间铺设了新光纤,并表示升级后该链路拥有“两个独立的通信路径”,以便在“一条路径中断”时设备仍能正常工作。停电发生十六个月后,费城TRACON失去了一条电路,发现另一条被切断,导致东北地区全部瘫痪。我无法确认这些是否是同一条线路,但它们属于同一设施。

We have run this experiment. After the Newark outages in the spring of 2025, the FAA laid new fiber between New York and Philadelphia and said the upgrade put the link on “two separate communications paths” so equipment would keep working “if one path is disrupted.”Sixteen months after those outages, Philadelphia TRACON lost one circuit, found the other cut and took down the Northeast. I cannot tell you those were the same lines. It was the same facility.

我们也在大规模上进行过类似实验。NextGen于2003年启动,承诺相同的目标。去年秋天,交通部监察长对其进行了审计:该项目在FAA和航空公司之间预计花费360亿美元,实际已花费超过150亿美元的FAA资金,且仅实现约16%的预期收益。备忘录指出的原因包括:缺乏明确要求、计划过于雄心勃勃以及项目相互依赖且航空公司未能按时采购设备。

We have also run it at scale. NextGen launched in 2003 with the same promises. Last fall the Transportation Department’s inspector general closed the books on it: a program projected at $36 billion between the FAA and the airlines, more than $15 billion of FAA money spent, and about 16 percent of expected benefits delivered. The memo’s causes: no firm requirements, overambitious plans and programs that depended on each other and on airlines buying equipment on schedule.

当前的努力显示了相同的模式。2025年7月,国会提供了125亿美元。上个月,贝德福德向国会报告称第一阶段花费已达160亿美元。新的请求将使总额达到425亿美元,而该部门去年提出的数字为315亿美元。政府问责局发现,FAA的第一阶段数字未计入政府费用、大部分运营费用以及全部第二阶段费用。

The current effort shows the pattern. Congress provided $12.5 billion in July 2025. Bedford told Congress last month that phase one is costing $16 billion. The new request would bring the total to $42.5 billion, against the $31.5 billion the department named last year. The Government Accountability Office found the FAA’s phase one figure leaves out government costs, most operations costs and all of phase two.

新增加的300亿美元中,只有约三分之一用于空中交通管制的架构和软件。其余部分分配给塔台、跑道和滑行道,以及中型机场的改进。那占三分之二的费用并未涉及导致故障的核心问题。

Only about a third of the new $30 billion is for air traffic control architecture and software. The rest is split between towers, runways and taxiways, and improvements at midsize airports. None of that two-thirds touches what failed.

还有那些在资金呼吁中很少出现的人。管制员必须在仍然执勤的情况下接受每个新系统的培训。技术人员必须在切换完成之前同时维护旧系统和新系统。我曾主持设施培训项目九年。过渡阶段是风险所在,而新自动化在减轻工作负荷之前会先增加工作量。

Then there are the people who rarely appear in these funding appeals. Controllers must be trained on each new system while still working the traffic. Technicians must maintain old and new side by side until the cutover is finished. I ran a facility training program for nine years. Transition is where the risk lives, and new automation adds workload before it removes any.

第一阶段计划将在2028年12月完成。政府问责局发现,联邦航空局正在运行11,389个独立的项目进度表,却没有总体进度表,且通常没有对其进行调整以减轻管制员的工作负荷。以这种方式进行的切换并不是现代化,而是新的隐患。

Phase one is due by December 2028. The GAO found the FAA running 11,389 separate project schedules with no master schedule, generally without adjusting them to reduce the load on controllers. A cutover run that way is not modernization. It is a new hazard.

因此,要有条件地提供资金。要求任何关键设施都不能依赖单一的物理通道,并通过测试加以证明。根据里程碑释放资金,并在每一批资金发放前让监察长和政府问责局进行报告。将管制员培训和技术人员配备与硬件放在同一法案中。并在投票前要求提供完整的全生命周期成本,而不是投票后才提供。Shedelbower本人写到“必要的投资和监督”。他主张首先进行投资。这是第二步。

So fund it, with conditions. Require that no critical facility depend on a single physical route, and prove it by test. Release the money against milestones, with the inspector general and GAO reporting before each tranche. Put controller training and technician staffing in the same bill as the hardware. And demand a full lifecycle cost before the vote, not after. Shedelbower himself writes of “necessary investment and oversight.”He argues for the first. This is the second.

Shedelbower询问旅客是否已经厌倦了延误,并告诉他们:“这就是答案。”金钱是其中的一个要素。答案是一个能够经受挖掘机冲击的计划。

Shedelbower asks whether travelers are sick of delays and tells them, “This is the answer.”Money is an ingredient. The answer is a plan that can survive a backhoe.

Vincent E. Bianco III 是 Marivin Consulting Services LLC 的首席顾问。他在 FAA 从事航空交通管制工作23年,曾担任管制员、质量保证与培训专家、一线经理以及航空交通经理。

Vincent E. Bianco III is principal consultant of Marivin Consulting Services LLC. He served 23 years in FAA air traffic control as a controller, quality assurance and training specialist, front-line manager and air traffic manager.