纽约市的办公楼改住宅热潮再度升温,距离曼哈顿中城一重大项目发生险些酿成灾难的事故、导致施工叫停并引发关于将办公大楼改为住宅安全性的新质疑,仅过去几个月。
New York City’s conversion boom is revving up again, only months after a near-disaster in Midtown Manhattan halted work on a major project and sparked new safety questions about turning office towers into housing.
自7月前辉瑞总部大楼两根结构柱因新增楼层重量而屈曲以来,市政府已检查了二十余个其他改建项目。
Since July, when two structural columns buckled under the weight of newly added floor space to the former Pfizer headquarters, the city has inspected two dozen other conversion projects.
建筑部认定该事故仅限于该单一建筑,不反映改建项目存在固有风险。据局长艾哈迈德·蒂加尼称,事故发生以来,该部门已为16个新项目发放了初步施工许可。
The Department of Buildings concluded that the accident was specific to that one building, and didn’t reflect an inherent risk related to conversions. Since the accident, the department has issued initial construction permits for 16 new projects, according to Commissioner Ahmed Tigani.
这一速度明显慢于上半年。部分原因是辉瑞大楼事故后,贷方和开发商对这类项目加强了审查。但也反映了近期利率上升拖慢了各类房地产开发。
That rate is considerably slower than the first half of the year. That is in part because of heightened scrutiny by lenders and developers of these projects after the Pfizer incident. But it also reflects the recent increase in interest rates that has slowed all kinds of property development.
目前,前辉瑞大楼——该市规模最大的办公楼改住宅项目,计划提供1600多套住房——工程已开始恢复。上周,开发商MetroLoft完成了一项精细作业,顶升下沉楼板并安装新钢支撑以替换受损柱子。
Now, work is beginning to resume at the former Pfizer building, which is the city’s largest office-to-apartment conversion project with more than 1,600 units planned. Last week, the developer, MetroLoft, completed a delicate operation to lift sagging floors and install new steel supports to replace damaged columns.
市政府仍在调查此次险些倒塌事故,该事故引发了稳固结构、疏散周边建筑及封锁市中心数个街区的紧急行动。官员尚未说明柱子为何缺乏必要加固。但蒂加尼表示,现在柱子已稳固,全面施工可能在几周内恢复。
The city is still investigating the near-collapse, which set off a scramble to stabilize the structure, evacuate nearby buildings and shut down several blocks in the heart of the city. Officials have yet to say why the columns lacked the necessary reinforcement. But now that the columns have been stabilized, full construction could resume within weeks, according to Tigani.
马马达尼政府指望办公楼改建帮助缓解该市住房短缺,预计未来几年此类项目可提供多达1.2万套公寓。蒂加尼说:“改建项目在其中发挥着重要作用。”
The Mamdani administration is counting on office conversions to help ease the city’s housing shortage, with as many as 12,000 apartments expected from such projects in the coming years. “Conversion projects play a big part of it,” Tigani said.
一个新项目将把布鲁克林市中心一座2023年竣工、从未招揽到办公租户的24层新建办公大楼的大部分楼层改建为公寓。一个由BH3 Management和Capstone Equities组成的合资企业,在上个月获得融资后,采取了转换策略;该企业去年以大幅折扣买下了该物业。
One new project will convert most of a new 24-story office tower in downtown Brooklyn that was completed in 2023 and never attracted an office tenant. A venture including BH3 Management and Capstone Equities, which received financing last month, adopted a conversion strategy after buying the property at a steep discount last year.
据BH3合伙人亚当·福克(Adam Falk)称,该大楼的现代化设计使其非常适合转换,无需进行重大结构变更。该合资企业预计将在18至20个月内完成转换,而从零开始开发一座新建筑通常需要四到五年时间。
The building’s modern design makes it well-suited for conversion without major structural changes, according to Adam Falk, a BH3 principal. The venture expects to complete the conversion in 18 to 20 months, compared with the four to five years it would typically take to develop a new building from the ground up.

同类建筑中的一居室公寓月租金约为5000美元,这与前任业主遭遇的疲软办公需求形成鲜明对比。福克说:“布鲁克林办公楼的故事充满了痛苦与挣扎。”
One-bedroom apartments in comparable buildings rent for about $5,000 a month, a contrast with the weak office demand the previous owner suffered. “The story of Brooklyn office is of a lot of pain and suffering,” Falk said.
这种痛苦帮助纽约成为全美将过时办公楼改建为公寓热潮的中心。此外,曼哈顿强劲的公寓租赁市场,以及使转换在财务上更具吸引力的城市和州级税收减免与分区法规变更,也在推动这一趋势。
That pain helped turn New York into the center of a nationwide boom in converting obsolete office buildings into apartments. Also fueling the trend: a strong Manhattan apartment rental market and city and state tax breaks and zoning changes that make conversions more financially attractive.
然而,这场热潮在7月突然蒙上阴影,当时辉瑞大厦发生结构失效,导致六个楼层下沉。警方和消防员紧急疏散该区域,生怕塔楼部分结构坍塌。
The boom was suddenly cast into doubt in July, when a structural failure at the Pfizer building caused six floors to sag. Police and firefighters scrambled to clear the area amid fears that part of the tower could come crashing down.
即使眼前的危险解除,这起事故仍为市政府官员、开发商和投资者提出了令人不安的问题:这只是孤立的施工失误,还是将老旧办公塔楼改建为公寓存在更广泛的安全隐患?
Even after the immediate danger passed, the accident raised troubling questions for city officials, developers and investors: Was this an isolated construction failure, or were there broader safety risks associated with turning aging office towers into apartments?
工程师表示,为改建而进行的建筑扩建可以安全完成。但要在任何原本并非为承受如此重量而建造的结构上加盖楼层,需要复杂的工程设计和精心的施工阶段排序。如果计算有误,可能在柱子得到适当加固之前就加盖楼层,结构可能会失效。
Engineers say building expansions for conversions can be done safely. But adding floors to any structure that wasn’t originally built to hold such weight requires complex engineering and careful sequencing of construction phases. If calculations are wrong, floors might be added before columns are properly reinforced and structures could fail.
自辉瑞事件以来,投资者和贷款方对现有和待建项目进行了广泛审查。法尔克说,他们“更仔细地审视了发起方及其经验”。
Since the Pfizer incident, investors and lenders have conducted extensive reviews of existing and pending projects. They looked “more closely at the sponsor and what their experience is,” Falk said.
建筑局对此作出回应,检查了与参与辉瑞项目的公司相关的180个建筑工地,其中包括24个办公楼改公寓项目。检查员在这些改建工地发现了三处违规,并签发了一份部分停工令,但未发现对公众构成紧迫危险的结构问题。
The Buildings Department responded by inspecting 180 construction sites associated with companies working on the Pfizer project, including 24 office-to-apartment conversions. Inspectors found three violations and issued one partial stop-work order at those conversion sites, but uncovered no structural problems posing an imminent danger to the public.
该市还对另外两个改建项目签发了停工令,分别位于百老汇大道222号和第三大道750号。这两份停工令此后均已解除,允许复工。
The city also issued stop-work orders at two other conversion projects, at 222 Broadway and 750 Third Avenue. Both orders have since been lifted, allowing work to resume.
危险源于扩建前辉瑞大楼所涉及的结构工程,这类施工并非改建项目所独有。
The danger arose from the structural work involved in expanding the former Pfizer building, a type of construction that isn’t unique to conversions.
“这并非办公楼改住宅改建所特有的问题,”蒂加尼说,“我们这里遇到的是对现有建筑进行的复杂扩建。”该市允许纽约最有经验的改建商MetroLoft恢复该项目部分低楼层的工作,这些楼层与9月份那次几近坍塌的事故无关。该公司拒绝置评。
“It wasn’t specific to the fact that it was office-to-residential conversion,” said Tigani. “What we had here was a complex enlargement of an existing building.”The city allowed MetroLoft, New York’s most experienced converter, to resume work on some lower floors of the project not involved in the near-collapse in September. The firm declined to comment.
尽管安全担忧有所缓解,改建的商业可行性却变得更加复杂。利率和建筑成本上升使项目更难获得融资。与此同时,办公楼市场正在复苏,这让一些业主有理由重新考虑将物业改造成公寓。
While safety concerns have eased, the business case for conversions has become more complicated. Elevated interest rates and construction costs are making projects harder to finance. Meanwhile, a recovering office market is giving some building owners reason to reconsider converting their properties into apartments.
仲量联行纽约地区研究主管梅拉妮·奥布莱恩表示:“写字楼市场的经济账正开始诱使业主坚守阵地。”
“The economics of the office market are starting to tempt owners to hold their ground,” said Melanie O’Brien, JLL’s head of research for the New York region.
信贷基金管理公司Northwind Group创始人兰·埃利亚萨夫表示,随着开发商耗尽最适合改造的楼宇供应,未来几年新改造项目的步伐可能会放缓。该公司活跃于为改造项目提供融资。
The pace of new conversions is likely to slow in the coming years as developers exhaust the supply of buildings best suited for redevelopment, according to Ran Eliasaf, founder of Northwind Group, a credit fund manager active in financing conversions.
但就目前而言,Northwind仍活跃于该市场。该公司最近为两个改造项目提供了融资,另有两笔针对中城项目的贷款正在运作中。
But for now, Northwind remains active in the market. The firm recently financed two conversions and has two more loans in the works for Midtown projects.
他说:“曼哈顿的公寓仍然严重短缺。改造是快速交付房源的好办法。”
“There’s still a big shortage of apartments in Manhattan,” he said. “Conversions are a great way to deliver units fast.”