政府计划在萨福克郡的西泽韦尔选址资助一座耗资数十亿英镑的核电站,政府支出监管机构认为,这在本世纪余下时间里对英国纳税人来说是一笔“糟糕的交易”。
The government’s plan to fund a multibillion-pound nuclear plant at the Sizewell site in Suffolk represents a “terrible deal” for the UK taxpayer over the rest of the century, according to the government’s spending watchdog.
公共账目委员会(PAC)的议员们警告政府,西泽韦尔C核反应堆的成本可能飙升至近480亿英镑,这将使缴费人不得不在2040年前再提供98亿英镑用于建设该电站,并在其60年的运营期内再提供120亿英镑。
MPs on the public accounts committee (PAC) have warned the government that the cost of the Sizewell C nuclear reactor could spiral to almost £48bn, leaving bill payers on the hook to provide an extra £9.8bn to construct the plant before 2040 and a further £12bn over its 60-year operating life.
公共账目委员会指出,纳税人和消费者面临“高水平风险”,因为政府同意持有这座核电站近45%的股份,该项目被视为萨默塞特郡欣克利角C核电站(该项目严重延期)的后续项目。
Taxpayers and consumers face a “high level of risk”, according to PAC, after the government agreed to take a near-45% stake in the nuclear plant, which is considered a successor project to the heavily delayed Hinkley Point C nuclear plant in Somerset.
根据这项数十亿英镑协议的条款,资金将通过税收和能源账单支付,英国政府持有44.9%的股份,而法国国有核电开发商EDF持有12.5%的股份。
Under the terms of the multibillion-pound deal, which will be paid for through taxes and energy bills, the UK government holds a 44.9% stake while French state nuclear developer EDF has a 12.5% stake.
其余资金来自私人投资者,包括英国天然气母公司Centric持有15%股份,加拿大投资集团La Caisse持有20%股份,以及投资管理公司Amber Infrastructure持有7.6%股份。
The rest of the funding has come from private investors including the British Gas owner Centrica, which holds a 15% share, alongside the Canadian investment group La Caisse, which holds 20%, and the investment manager Amber Infrastructure, which has a7.6% stake.
在因国家安全担忧浮现之前,中国国有核电开发商中广核(CGN)曾被允许持有西泽韦尔C 20%的股份;英国政府被迫收购了中广核的股份,从而不得不承担比预期更大的项目份额。
The UK government was forced to take a larger than expected share of the project after buying out Chinese state nuclear developer CGN, which had been allowed to hold a 20% stake in Sizewell C before national security concerns emerged.
监管机构警告称,虽然英国公众可能被要求承担数十亿英镑的成本超支,但该核电项目的私人投资者只需额外投入3000万英镑。
The watchdog warned that while the British public could be called on to shoulder multibillion-pound cost overruns, the nuclear project’s private investors would only need to put in an extra £30m.
公共账目委员会(PAC)主席杰弗里·克利夫顿-布朗爵士表示:“纳税人和消费者为西泽韦尔C核电站建设所承担的高风险水平令人震惊。私人投资者似乎将获得可观的投资回报,而客户则可能被迫承担更高的能源账单。”他敦促政府“专注于成功交付该项目”,并在更广泛地建立对英国核工业的信心,以便纳税人“永远不会再被置于这种境地”。
Sir Geoffrey Clifton-Brown, the PAC chair, said: “The high level of risk borne by taxpayers and consumers for the construction of Sizewell C is extraordinary. Private investors look set for significant returns on their investments, while customers are likely to be saddled with higher energy bills.”He urged the government to “focus on the successful delivery of this project”, and in building confidence in the UK’s nuclear industry more broadly, so that taxpayers will “never be put in this position again”.
一位政府发言人表示,该报告“完全忽视了投资者受交易条款激励,要以尽可能低廉和快速的方式完成建设”。
A government spokesperson said the report “completely ignores that investors are incentivised to complete construction as cheaply and quickly as possible” through the terms of the deal.
该发言人补充道:“一旦投入运营,西泽韦尔C每年可为能源系统节省20亿英镑,降低全国各地家庭的成本,该项目目前已取得良好进展,现场有超过2000名工人在施工。”
“Once operational, Sizewell C could save £2bn a year across the energy system, cutting costs for families up and down the country, and the project is already making good progress with over 2,000 workers on site,” the spokesperson added.
政府预计西泽韦尔C的成本将在405亿至477亿英镑之间,建设将于2039年至2043年间完成。委员会呼吁政府在未来三个月内提供其用于支撑项目成本估算的情景分析。委员会还要求部长们每六个月提供一次项目进展更新,以便跟踪其进度。
The government expects Sizewell C to cost between £40.5bn and £47.7bn and to complete construction between 2039 and 2043. The committee has called on the government to provide the scenario analysis it used to underpin its cost estimates for the project within the next three months. It also asked ministers to provide an update on the project’s development every six months to keep track of its progress.
该项目的批评者,包括“停止西泽韦尔C”运动组织的艾莉森·唐斯和格林威治商学院的史蒂夫·托马斯教授,他们曾向委员会提交联合证词,指出放弃该项目的当前成本将低于在60年内支付膨胀的能源账单的成本“数倍之多”。
Critics of the project, including Alison Downes of the Stop Sizewell C campaign group and Prof Steve Thomas of Greenwich Business School, who provided joint evidence to the committee, have suggested that the cost of abandoning the project today would be lower than the cost of paying inflated energy bills over 60 years “multiple times over”.
他们呼吁政府排除将这种融资模式用于未来核电项目的可能性。他们在一份联合声明中表示:“这只会给投资者提供免费搭便车的机会,却让家庭承受经济痛苦。”
They called on the government to rule out using this funding model for future nuclear projects. “All it offers is a free ride for investors and financial pain for households,” they said in a joint statement.
核工业协会首席执行官汤姆·格雷特雷克斯表示,西泽韦尔C核电站将提供“清洁、可靠且持续可用的电力”,这能让家庭省去数十亿英镑的电网平衡成本或额外网络连接建设费用。
Tom Greatrex, the chief executive of the Nuclear Industry Association, said Sizewell C would provide “clean, reliable and constantly available power” that could save households billions from paying the cost of balancing the grid or building extra network connections.
他说:“目前,消费者今年迄今已承担了28亿英镑的账单,用于管理一个功能失调的电网,既要为风电在某些时段停止发电买单,又要为燃气备用电源在其他时段发电买单。”
“Currently, the consumer is footing a bill of £2.8bn so far this year to manage a dysfunctional grid, paying both for wind to stop generating at some times, and for gas-powered backup at others,” he said.