Lithium Americas周三将其在内华达州Thacker Pass锂项目一期的估算成本上调31%至38亿美元,原因是劳动、建筑和物流成本上涨。
该修订估算增加了8亿美元9500万美元的额外资本支出,使项目的资金需求增加约9亿美元,公司表示。
Lithium Americas on Wednesday raised the estimated cost of Phase 1 of its Thacker Pass lithium project in Nevada by 31% to $3.83 billion, citing higher labor, construction and logistics costs.
Lithium Americas表示,预计将通过贡献和可用的美国能源部贷款储备来覆盖更高的资金需求,关税和物流成本约占增加额的1亿美元,而管道、钢材和设备的焊接安装费率上涨增加了2.45亿美元。公司预计今年将在一期项目上花费17亿美元至20亿美元,此前估算为13亿美元至16亿美元。一期项目预计将在2028年达到商业生产,年产量为4万吨。
Thacker Pass是Lithium Americas与美国汽车制造商通用 Motors(GM.N)的合资项目,拥有足够的锂储量建造100万辆电动汽车。Lithium Americas在9月30日拥有约13亿美元的现金及受限现金,其中约3600万美元在Thacker Pass合资企业中。
The revised estimate adds $895 million in incremental capital expenditure and increases the project's funding requirement by about $995 million, the company said. Here are more details: Lithium Americas said it expects to cover the higher funding requirement through contributions and available Department of Energy loan reserves Tariff and logistics costs accounted for about $100 million of the increase, while higher labor installation rates for piping, steel and equipment added $245 million The company expects to spend $1.7 billion to $2.0 billion on Phase 1 this year, up from its prior estimate of $1.3 billion to $1.6 billion Phase 1 is expected to ramp up to commercial production in 2028 and produce a nominal 40,000 tons annually at full capacity Thacker Pass is a joint venture between Lithium Americas and US automaker General Motors (GM.N) and holds enough lithium to build 1 million electric vehicles annually Lithium Americas had about $1.3 billion in cash and restricted cash as of September 30, including about $360 million held at the Thacker Pass joint venture