一名前任维多利亚州长丹尼尔·安德鲁斯的顾问已收到强制出庭通知,须出席“大建设”皇家委员会听证,周四的听证会获悉此事。
A former adviser to then Victorian premier Daniel Andrews has received a compulsory notice to appear before the Big Build royal commission, a hearing was told on Thursday.
照片:Diego Fedele/AAP 一位长期担任维多利亚州长的丹尼尔·安德鲁斯的前顾问将被强制出席皇家委员会,此前一个因未向调查人员移交证据而受到批评的政府机构披露了一系列关于一个有争议铁路项目的短信。
Photograph: Diego Fedele/AAP A former adviser to longtime Victorian premier Daniel Andrews will be forced before a royal commission after a government agency that was criticised for failing to hand over evidence to investigators disclosed a series of text messages about a controversial rail project.
周四,调查维多利亚州重大公共和土木基础设施建设项目廉洁性的皇家委员会获悉,维多利亚基础设施交付局未能提供相关文件,或提供了经过不当涂黑处理的文件。
The commission into the integrity of major public and civil infrastructure construction projects in Victoria heard on Thursday that the Victorian Infrastructure Delivery Authority (Vida) had failed to produce relevant documents or produced documents that were improperly redacted.
协助委员会的资深大律师克里斯·杨表示,考虑到现任州长本·卡罗尔多次强调委员会工作的重要性,维多利亚基础设施交付局的态度令人特别失望,并提醒现任和前任公务员,不遵守规定可能会被判处监禁。
The counsel assisting the commission, Chris Young KC, said Vida’s attitude was particularly disappointing given the current premier Ben Carroll’s repeated comments about the importance of the commission’s work, and reminded current and former public servants that failure to comply could be punished with imprisonment.
本周委员会首次听取了公开证人的证词,听证重点关注建筑、林业和海事雇员联合会(CFMEU)在2022年桑伯里盖普路平交道拆除项目中的参与情况。
The commission has heard from public witnesses for the first time this week, with the hearings focusing on the Construction, Forestry and Maritime Employees Union’s (CFMEU) involvement in a 2022 level crossing removal Gap Road in Sunbury.
杨表示,维多利亚基础设施交付局曾多次申请延长向委员会提供文件的期限,随后在截止日期过后两天提供了一份文件,其中包含数页经过不当涂黑处理的手写笔记,这些笔记是盖普路项目的核心内容。
Young said that Vida requested multiple extensions to a deadline to provide documents relevant to the commission, and then provided a document two days late that included pages of handwritten notes that had been improperly redacted that were central to the Gap Road project.
杨周二晚间表示,维多利亚基础设施交付局还首次披露了其人员持有的直接涉及该项目的短信的存在。
On Tuesday night, Young said Vida also disclosed for the first time the existence of text messages held by its personnel directly concerning the project.
这些短信涉及PPO(即州长私人办公室),以及安德鲁斯的前顾问马修·托纳,和维多利亚基础设施交付局前幕僚长马修·费兰。
Those messages include references to the PPO, or the Premier’s Private Office, and to Matthew Toner, a former adviser to Andrews, and Matthew Phelan, a former chief of staff at Vida.
杨说,托纳于2024年初离职,大约就是安德鲁斯辞去州长职务的时间。
Young said Toner left his position in early 2024, about the time Andrews resigned as premier.
他说,2024年3月14日CFMEU代表会议的记录显示,该工会前州秘书约翰·塞特卡表示托纳已离职,并称“他对工会是个很好的资产”。
He said that notes from a CFMEU delegates meeting on 14 March 2024 recorded its former state secretary John Setka as saying Toner had left and that “he was a good asset to the union”.
专员克里斯托弗·库拉基斯确认,自短信被发现以来,托纳和费兰已被发出强制通知,要求出席委员会作证。周四,杨说委员会完成工作的时间所剩无几。
The commissioner, Christopher Kourakis, confirmed that Toner and Phelan had been issued compulsory notices to appear before the commission since the texts were uncovered. On Thursday, Young said the commission only had a short time to complete its work.
杨说:“它拥有强制权力,并有制裁措施予以强化……其中包括监禁。”
“It has compulsory powers, reinforced by sanctions … which do include imprisonment,” Young said.
杨补充道:“理应预期,国家机关会看到并理解本委员会工作的重要性,并遵守《调查法》强加给它们的义务。”他指出,非国家当事方已遵守强加给他们的要求,“这些要求至少同样繁重”——而且遵守得快得多,并指出国家当事方的拖延已经影响了听证会的时间表。
“It might be expected that agencies of the state would see and understand the significance of the work of this commission and comply with the obligations imposed on them by the Inquiries Act.”Young added that non-state parties had complied with the requirements imposed on them that “are as least as onerous” – and had done so far quicker, noting that the delays from state parties had already affected the timetable of hearings.
杨说:“考虑到该州州长关于本委员会重要性、其工作重要性以及将获得国家配合的一切表态,国家实体以及现任和前任高级国家官员及其雇员,只有在被强制时才与本委员会接触,否则似乎甘愿什么都不做,除非被强制,这令人深感失望。”
“It is profoundly disappointing in light of everything that has been said by the premier of this state about the importance of this commission, about the importance of its work, and about the cooperation it would receive from the state, that state entities and senior current and former state officers and their employees, only engage with this commission when compelled to do so, and seem otherwise content to do nothing, unless compelled,” Young said.
杨说,维达迟交的材料中包括与委员会核心会议相关的手写笔记,且涂黑处理不当。
Among the material handed over late by Vida were improperly redacted handwritten notes regarding meetings central to the commission, Young said.
这八页笔记来自维达前高管埃文·塔特萨尔,其中包括最终得以解决的那场劳资纠纷当天上午会议的记录,记录中指出:“主张 RIA[铁路基础设施联盟]未与CFMEU接触”。
The eight pages of notes, from former Vida executive Evan Tattersall, included those taken from a meeting the morning the industrial dispute that was eventually resolved, which noted “Claim RIA [Rail Infrastructure Alliance] hasn’t engaged with CFMEU”.
Vida 的代理律师、御用大律师 Richard Knowles 表示,该机构打算尽快回应委员会要求提供更多文件的请求。“我们理解所言事态的严重性,”Knowles 说。
Richard Knowles KC, for Vida, said the agency intend to respond as soon as possible to requests for more documents from the commission. “We understand the gravity of what has been said,” Knowles said.
“我们确实重申致力于竭尽所能协助皇家委员会的调查,如有任何不足之处,我们深表歉意。” 听证会还听取了建筑公司 John Holland 两名证人的证词,该公司受聘作为联盟成员(与州政府及其他公司组成联盟)负责实施 Gap Road 项目。
“We do affirm our commitment to assist the royal commission in its inquiries to the best of our abilities and to the extent that there may have been any falling short, we apologise.”The commission also heard from two witnesses from construction company John Holland, contracted to deliver the Gap Road project as part of an alliance with the state government and other companies.
该公司产业关系经理 Stephen Beirne 告诉委员会,自 2022 年澳大利亚建筑与施工委员会(ABCC)被废除后,建筑行业在威慑违反《公平工作法》的行为方面几乎没有选择。
Stephen Beirne, an industrial relations manager at the company, told the commission that, after the Australian Building and Construction Commission (ABCC) was abolished in 2022, the construction industry had few options when it came to deterring breaches of the Fair Work Act.
该公司产业关系总经理 Trent Smith 告诉委员会,公司内部认为,由于历史上存在“敌对”打交道的经历,在维多利亚州与 CFMEU 打交道比在其他州更困难。听证会继续进行。
The company’s general manager of industrial relations, Trent Smith, told the commission that there was a view within the business that dealing with the CFMEU in Victoria was more difficult than in other states, due to historical “hostile” dealings. The hearing continues.