发布时间:2026-11-19T08:54:52+08:00 据知情人士透露,蓝猫头鹰资本公司(Blue Owl Capital Inc.)正准备出售5.13亿美元商业抵押贷款支持证券(CMBS),为收购弗吉尼亚州北部一座数据中心融资,该数据中心已全部出租给亚马逊公司。

Published: 2026-11-19T08:54:52+08:00 Blue Owl Capital Inc. is preparing to sell $513 million of commercial mortgage backed securities to fund the acquisition of a Northern Virginia data center that’s fully leased to Amazon.com Inc., according to people with knowledge of the matter.

知情人士称,此次融资由花旗集团牵头,其中包括3.75亿美元债券,平均期限约五年,预计将获得惠誉评级和克罗尔债券评级机构的AAA评级。他们补充说,该档债券的初始价格指引约为基准利率加1.95个百分点。这些人士因讨论保密交易条款而要求匿名。

The financing, which is being run by Citigroup Inc., includes $375 million of bonds with an average life of about five years that are expected to be rated AAA by Fitch Ratings and Kroll Bond Rating Agency, the people said. The initial price talk for the tranche is about 1.95 percentage points over the benchmark, they added, asking not to be named discussing confidential deal terms.

知情人士称,另有约1.12亿美元部分,平均期限同样约为五年,预计将获得克罗尔的AA评级,初始价格指引约为基准利率加2.6个百分点。他们补充说,剩余约2600万美元部分预计将获得克罗尔的AA-评级,正在进行私募配售。蓝猫头鹰和花旗集团的发言人均拒绝置评。

Another roughly $112 million portion, also with an average life of about five years, is expected to be rated AA by Kroll, with initial price talk at about 2.6 percentage points over the benchmark, the people said. A remaining roughly $26 million portion, expected to be rated AA- by Kroll, is being privately placed, the people added. Representatives for Blue Owl and Citigroup declined to comment.

知情人士称,这笔单一资产、单一借款人的CMBS由“Crossing III项目”数据中心的抵押贷款支持,该数据中心装机容量为54兆瓦。亚马逊的租约于3月开始,持续至2041年,并有两个五年续约选择权。亚马逊并未参与安排此次融资。

The single-asset, single-borrower CMBS is backed by the mortgage on the 54 megawatt Project Crossing III data center, the people said. Amazon’s lease began in March and runs through 2041, with two five-year renewal options. The company isn’t involved in arranging the financing.

该物业是盖恩斯维尔Crossing数据中心园区的第三座数据中心。知情人士称,该园区最终预计将包含五座设施,总容量达326兆瓦。

The property is the third data center in the Gainesville Crossing Data Center campus. The campus is expected to eventually include five facilities totaling 326 megawatts of capacity, people said.