据德国《BILD》报纸周四报道,在德国海军取消F126护卫舰项目的背景下,荷兰造船公司Damen要求德国政府赔偿近47亿欧元(约合52.3亿美元)。
Dutch shipbuilder Damen is seeking nearly €4.7 billion ($5.23 billion) from the German government after the cancellation of the navy’s F126 frigate program, the German newspaper BILD reported Thursday.
报道称,Damen的律师彼得·高威尔(Peter Gauweiler)已致函德国联邦议院的预算委员会和国防委员会成员,要求政府支付46.79663394亿欧元。高威尔表示,这笔款项属于德国政府根据合同应支付的款项,并非额外的赔偿金。
Damen’s lawyer Peter Gauweiler sent a letter to members of the Bundestag’s budget and defense committees demanding €4,679,663,394, according to the report. Gauweiler argued that the figure concerns payments the federal government committed to under the contract, rather than an additional claim for damages.
他强调,国防部长鲍里斯·皮斯托瑞乌斯(Boris Pistorius)终止合同的行为并未免除德国政府的这些支付义务;此外,这笔款项中的大部分将用于支付Damen在德国的数百家分包商的款项。报告还指出,Damen对公司损失的评估尚未完成,因此未来可能还会提出进一步的索赔要求。
He said Defense Minister Boris Pistorius’ termination of the contract did not remove those obligations, and that a substantial share of the money would go to hundreds of Damen’s subcontractors in Germany. The company’s assessment of its losses remains incomplete, meaning further claims could follow, according to the report.
据报道,这封函件中包含一封日期为9月22日的信件,信中指控德国国防部高级官员存在滥用职权的行为。Damen要求政府作出具有法律约束力的承诺,以弥补因这些违规行为而造成的现有及未来的损失。
Allegations against ministry The correspondence reportedly included a letter dated Sept. 22 addressed to Pistorius, alleging that suspicions of abuses of authority by senior Defense Ministry officials had intensified. Damen requested a legally binding commitment from the ministry to cover existing and future losses arising from the alleged breaches.
这些指控是围绕F126护卫舰项目取消所引发的争议的一部分。虽然Damen是该项目的主要承包商,但这些护卫舰实际上应在德国的沃尔加斯特(Wolgast)、基尔(Kiel)和汉堡(Hamburg)等造船厂建造。皮斯托瑞乌斯于6月24日以项目进度严重滞后、成本不断上升以及风险难以预测为由终止了该项目;据报道,根据德国国防部的估算,完成该项目可能需要高达18亿欧元的资金。
The allegations are part of an escalating dispute about the cancellation of a program to build six F126 frigates, one of the navy’s largest modernization projects. Although Damen was the main contractor, the ships were to be built entirely at German shipyards in Wolgast, Kiel and Hamburg. Pistorius halted the project on June 24, citing severe delays, rising costs and unpredictable risks. Completing the program could have cost as much as €18 billion, according to the ministry’s calculations cited in the report.
Damen公司对政府的解释表示质疑,并认为该项目被取消具有政治动机。该公司还指出,德国政府在2024年6月仍决定根据该计划再订购两艘护卫舰。
Germany considers counterclaim Damen disputes the government’s explanation, arguing that the cancellation was politically motivated. The company also points to Berlin’s decision in June 2024 to order two additional frigates under the program.
皮斯托瑞斯在7月份否认了这些指控,将合同终止的原因归咎于承包商的表现不佳且工作不彻底,并表示这一决定是必要的,目的是为了保护纳税人的利益。
Pistorius rejected the allegations in July, attributing the termination to the contractor’s poor and incomplete performance and defending the decision as necessary to protect taxpayers’ money.
据报道,德国政府正在准备向Damen公司提出高达23亿欧元的索赔。
The German government is preparing a potential €2.3 billion claim for damages against Damen, according to the report.