芬兰电网运营商Fingrid Oyj表示,未来五年该国电力需求预计将增长高达40%,主要由规划中的数据中心推动。

Finland’s power network manager Fingrid Oyj said the power demand in the country is set to grow as much as 40% over the next five years, led by planned data centers.

这家总部位于赫尔辛基的公司周五在其网站上表示,生产热能的锅炉项目和储能项目也助推了需求增长,需求增幅之大导致电网接入申请的处理出现积压。

Boilers producing heat and energy storage projects also contribute to the demand that’s risen so much that it’s caused a logjam in the processing of grid connection applications, the Helsinki-based company said on its website Friday.

Fingrid称,截至10月中旬,已有超过5吉瓦的数据中心项目签署了电网接入协议,其中包括配电网项目。这一数字超过了芬兰五座核反应堆的总发电量,后者约为4.4吉瓦。

More than 5 gigawatts of data center projects have signed grid connections by mid-October, including in distribution networks, Fingrid said. That’s more than the combined output of Finland’s five nuclear reactors, which is about 4.4 gigawatts.

这一激增是数据中心开发更广泛浪潮的一部分,正在重塑欧洲和美国的电力市场,因为人工智能和云计算推动了对海量电力的需求。项目间为争夺稀缺的电网容量而竞争,迫使电网运营商加速投资,同时也引发了关于谁优先获得电网接入的问题。

The surge is part of a broader wave of data-center developments that is reshaping power markets across Europe and the US as artificial intelligence and cloud computing drive demand for vast amounts of electricity. Projects are competing for scarce grid capacity and are forcing network operators to accelerate investment, while raising questions over who gets priority to the network.

Fingrid表示,正在建设和运营的锅炉项目超过3吉瓦,尽管设施通常以较低容量运行。在建储能项目总计近6吉瓦。

Boiler projects being built and operated account for more than 3 gigawatts, although facilities are usually run at lower capacity, Fingrid said. Energy storage projects in the pipeline total almost 6 gigawatts.

如果所有规划项目均落地,与去年水平相比,用电量将增加高达40%。

If all the planned projects are realized, electricity consumption will increase by as much as 40% relative to last year’s level.

芬兰政府正在起草一项法律,将赋予关键基础设施项目电网接入优先权,优先于数据中心等设施。政府还于周四提议收紧外国直接投资规则,要求特定项目(如装机容量100兆瓦或以上的数据中心,以及人工智能和量子计算处理项目)申请许可。

Finland’s government is working on a law that would give critical infrastructure projects a priority for grid connections over facilities like data centers. It also on Thursday proposed tightening foreign direct investment rules by requiring permits for certain projects, such as data centers of 100 megawatts or more, and AI and quantum computing processing.