Nextdc Ltd. 首席执行官将放弃 2027 财年短期激励和长期激励机会,此前这家澳大利亚数据中心开发商因墨尔本一项重大项目的电力供应延迟而下调盈利指引。
Ltd.’s CEO will give up his FY27 short term incentive and long-term incentive opportunities after the Australia data center developer cut its earnings guidance due to delayed power supply at one of its major projects in Melbourne.
董事长 Douglas Flynn 表示:“董事会和管理层专注于两大优先事项:与客户和配电商合作,将 M3 电力延迟的影响降至最低,以及重获投资者和其他利益相关者的信心。”
“The board and management are focused on two priorities: working with our customer and the electricity distributor to minimize the impact of the M3 power delay, as well as earning back the confidence of our investors and other stakeholders,” said Chairman Douglas Flynn.
根据下月股东周年大会前发布的声明,Flynn 和公司非执行董事也同意将其酬金削减 10%。董事会撤回了一项决议,该决议原拟寻求股东批准将非执行董事最高年度薪酬上限增加 30 万澳元,从 220 万澳元增至 250 万澳元。
Flynn and the company’s non-executive directors have also agreed to a 10% reduction in their fees, according to a statement ahead of the company’s annual general meeting next month. The board withdrew a resolution to seek shareholder approval to increase the maximum annual remuneration of non-executive directors by A$300,000, to A$2.5 million from A$2.2 million.
CEO Craig Scroggie 不会因放弃激励而获得任何现金或其他形式的替代奖励。
CEO Craig Scroggie will not receive any cash or other award in place of his relinquished incentives.
此前,公司位于墨尔本西郊的 M3 数据中心发生电力延迟,导致股价自 2010 年上市以来最大跌幅,并迫使公司将全年盈利指引削减三分之一。
It comes after a power delay at the company’s M3 data center in the Western suburbs of Melbourne prompted the biggest drop since the company listed in 2010 and forced it to slash full-year earnings guidance by a third.
Flynn 重申,在短暂交接期后,一旦新任主席到位,他将有意从董事会退休。
Read: AI Data Center Anger Threatens Australia’s $70 Billion Dream Flynn reaffirmed his intention to retire from the board once a new chairman is in place, after a short handover period.
声明称,全球搜寻和董事顾问公司 Spencer Stuart 已受聘寻找一名独立非执行董事和新任主席。Nextdc 表示,新任非执行董事最好具备数据中心、能源或基础设施开发及资本管理经验。
Global search and board advisory firm Spencer Stuart has been hired to find an independent non-executive director and a new chair, according to the statement. The new non-executive directors will ideally have data center, energy or infrastructure development and capital management experience, Nextdc said.