有限公司正在考虑不可抗力选项,并下调了盈利指引,此前社区反对导致其位于墨尔本的一座主要数据中心的电力供应延迟。

Ltd. is considering force majeure options and cut earnings guidance after community opposition delayed power supply to one of its major data centers in Melbourne.

这家澳大利亚数据中心开发商在提交给澳大利亚证券交易所的声明中表示,其息税折旧摊销前利润(EBITDA)已从3.85亿至4.10亿澳元下调至2.45亿至2.65亿澳元(约合1.72亿美元)。

The Australian data center developer said its earnings before interest, taxes, depreciation, and amortization was revised to between A$245 million ($172 million) and A$265 million, down from A$385 million to A$410 million, in a statement to the Australian stock exchange.

该公司还在审查其资本支出计划,并暂停所有新开发项目和土地收购。

The company is also reviewing its capital expenditure program, and placing all new development projects and land acquisitions on hold.

声明称,此次盈利下调源于电力供应延迟——Jemena Electricity Networks因社区和利益相关方的反对而暂停了电力接入工程。

The earnings downgrade comes after a power delay due to Jemena Electricity Networks suspending electricity connection works in response to community and stakeholder opposition, according to the statement.

“Nextdc正在考虑是否可以依据这些合同中的不可抗力条款及其他相关条款获得救济,”该公司在文件中表示。

“Nextdc is considering whether relief is available to it under the force majeure and other relevant provisions of those contracts,” the company said in the filing.

甲骨文数据中心之争为活动人士提供全美出击路径。该公司表示,已在可预见的未来暂停所有新开发项目和土地收购。“董事会还将评估资本回收机会,包括可能出售短期内不需要的部分开发地块,”Nextdc表示。

Oracle Data Center Fight Hands Activists Path to US-Wide Blitz The company said it has put all new development projects and land acquisitions on hold for the foreseeable future. “The board will also evaluate capital recycling opportunities, including the potential sale of selected development sites that are not required in the near term,” Nextdc said.

这一挫折凸显了澳大利亚数据中心建设潮面临的挑战。澳大利亚联邦银行估计,到2030年该领域投资可能达到1500亿澳元。这些高耗能设施需要可靠的24小时电力供应,而与此同时,该国正在关停老化的燃煤电厂,并更加依赖波动性的风能和太阳能。除非发电、储能和电网容量方面的投资同步跟进,否则计划中的扩张可能会被推迟。

The setback highlights a challenge confronting Australia’s data-center buildout, which Commonwealth Bank of Australia estimates could reach A$150 billion by 2030. The energy-hungry facilities require reliable around-the-clock electricity supply, just as the country is retiring aging coal plants and relying more heavily on variable wind and solar. Unless investment in generation, storage and grid capacity keeps pace, the planned expansion could be delayed.