东京 —— 日本工程集团 IHI 已接获美国核电公司西屋电气的订单,将为波兰核电站的建设提供关键设备。
TOKYO -- Japanese engineering group IHI has received an order from U.S.-based nuclear power company Westinghouse Electric toward supplying key equipment for the construction of a nuclear plant in Poland.
该工程集团签署了一份涉及 1 号机组安全壳及钢模块的设计与材料采购的初步合同,该机组是计划建设的三座反应堆之一。IHI 旨在争取后续涵盖设备制造与交付的合同。这些额外合同有望使订单总额超过数十亿日元(10 亿日元约合 634 万美元)。
The engineering group signed a preliminary contract involving design and materials procurement for the containment vessel and steel modules of the plant's Unit 1, one of three reactors to be built. IHI aims to secure follow-on contracts covering the manufacturing and delivery of the equipment. Those additional contracts could lift the total order value beyond several billion yen (1 billion yen equals $6.34 million).
该核电站将是波兰的首座核电站,目标于 2036 年投入运营。IHI 希望最早于 2028 年初在位于东京附近横滨的工厂开始制造工作,相关部件将分段出口。公司还计划争取另外两座反应堆的订单。
The nuclear power plant, targeted to begin operation in 2036, will be Poland's first. IHI hopes to work on manufacturing as early as the beginning of 2028 at its plant in Yokohama, near Tokyo, with the components to be exported in separate sections. The company aims to secure orders for the other two reactors as well.
该电站将采用西屋电气最先进的 AP1000 反应堆,这是一种大型轻水反应堆,安全性评价极高。每座反应堆额定输出功率约为 120 万千瓦。
The plant will use Westinghouse's state-of-the-art AP1000 reactor, a large light-water reactor rated highly for safety. Each reactor will have a rated output around 1,200 megawatts.
IHI 此前曾为同型号反应堆制造过安全壳,包括美国佐治亚州沃格特尔核电站的两座。这帮助 IHI 从西屋电气获得了这份初步协议,也是该公司约十年来首次获得此类订单。
IHI has fabricated containment vessels for the same reactor model before, including two at Vogtle Electric Generating Plant in the U.S. state of Georgia. This helped IHI get the preliminary agreement from Westinghouse, its first such order in around a decade.
安全壳是直径 40 米、高度超过 60 米、重量约 4000 公吨的巨大圆筒。钢模块安装在安全壳内部,以辅助混凝土墙的快速施工。
The containment vessels are massive cylinders 40 meters across and over 60 meters high, weighing around 4,000 metric tons. Steel modules are installed inside the vessels to aid in quick construction of concrete walls.
IHI 将核电定位为增长领域,目标是到 2032 年 3 月结束的财年,通过日本国内核电站重启及海外新建项目,将该板块销售额提升至 1000 亿日元以上。
IHI positions nuclear power as a growth area, and aims to increase sales in the segment to over 100 billion yen by the fiscal year ending March 2032 through work on plant restarts in Japan and new construction projects overseas.
该工程集团计划在三年内投资约200亿日元,用于升级横滨工厂的设备,并将另一座工厂的部分产能转为核能相关业务。
The engineering group plans to invest roughly 20 billion yen over three years to upgrade equipment at the Yokohama facility and convert part of another plant for nuclear-related work.