甲骨文公司正在采用一种创新的能源策略,以确保其多个数据中心项目按计划推进:将天然气直接通过卡车运送到服务器集群。
Corp. is using a novel power strategy to keep several data centers on track: trucking natural gas directly to the server farms.
据熟悉该项目的人士透露,在甲骨文等待天然气管道建成并与设备连接期间,卡车运输使位于盐湖城郊外的一座数据中心持续运行了一年多。其中一位人士还表示,该公司也采用这种方式,在得克萨斯州沙克尔福德县为 OpenAI 建设的一个园区内开展初期工作。
The truck deliveries kept a data center on the outskirts of Salt Lake City moving forward for more than a year as Oracle waited for a gas pipeline to be built and integrated with its machinery, according to people familiar with the work. The company also is using this approach to get initial work done at one of its campuses being built for OpenAI in Shackelford County, Texas, one of the people said.
目前,据熟悉该项目的人士称,甲骨文正在考虑在新墨西哥州采用同样的策略。当地一条用于为其最重要的数据中心之一供气的天然气管道项目出现延误,威胁到整个项目的进度。这些人士称,名为“木星计划”的卡车运输压缩天然气方案,将让该公司在管道正式启用前,率先启动项目初期阶段。由于该策略尚未公开,他们要求匿名。
Now, Oracle is considering using the same strategy in New Mexico, where a gas pipeline to help power one of its most crucial data centers is delayed and threatening the project’s timeline, according to people familiar with the project. A plan to use trucks to deliver compressed natural gas to the data center, called Project Jupiter, would let the company get the early stages of it online before the pipeline enters service, said the people, who asked not to be identified because the strategy hasn’t been made public.
此次事件风险极高。上个月,甲骨文以“不可抗力”为由,向新墨西哥州项目开发商发出通知,此举可能使公司在项目进一步延误的情况下免于支付部分款项。
The stakes are high. Last month, Oracle sent a notice citing force majeure to the New Mexico project’s developer, which may shield the company from making some payments in case of further delays.
甲骨文未回应置评请求。该报道发布后,其股价下跌约 5.5%。
Oracle didn’t respond to a request for comment. The shares dropped about 5.5% after the report.
能源供应已成为人工智能数据中心发展浪潮中的主要瓶颈。许多大型服务器集群项目都采用现场发电厂,通过燃烧天然气来提供电力。天然气通常通过管道输送,而管道的规划和建设往往需要数月时间。
Power has emerged as a major bottleneck to the AI data center boom. Many of the significant server farm developments are using on-site power plants that burn natural gas to provide electricity. The gas would typically be delivered by a pipeline, which can take months to design and build.
管道项目也可能因监管行动而延迟。在新墨西哥州,管道运营商 Energy Transfer LP 最初提出的一条路线遭到州监管机构否决,因此不得不为最终将为甲骨文数据中心供能的项目重新规划路线。这导致该管道公司的计划投用日期从今年夏天推迟到了明年。
Pipelines can also be delayed by regulatory action. In New Mexico, pipeline operator Energy Transfer LP had to reroute the project that will ultimately power Oracle’s data center after a proposed route was rejected by state regulators. That pushed the pipeline firm’s targeted in-service date to next year, rather than this summer.
鉴于快速保障天然气供应所面临的挑战,一批专门从事天然气压缩和卡车运输的公司,抓住了数据中心开发商急于尽快启动计算能力的热潮。包括 Superior Plus Corp. 旗下的 Certarus 和 VoltaGrid LLC 在内的这些企业,正在推广其所谓的“虚拟管道服务”,将其定位为在等待管道正式投用期间的过渡性供电方案。
Given the challenges to quickly ensure a supply of gas, a cluster of companies that specialize in compressing gas and transporting it via truck have seized on the frenzy by data center developers to start generating computing power as quickly as possible. These firms, including Superior Plus Corp.’s Certarus and VoltaGrid LLC, are pitching their so-called virtual pipeline services as a transitional power solution while waiting for a pipeline to come online.
通过卡车运输压缩天然气既不易也不便宜。East Daley Analytics 的高级能源分析主管 Jack Weixel 表示,如果计入人工、专业设备以及卡车本身的燃料成本,最终送达的成本大约是经由大型管道枢纽输送的天然气价格的四倍。天然气必须先从管道中抽出,压缩装入拖车,有时还要经过数小时运输才能到达目的地,然后再进行解压以填充发电机。即使是一个相对较小的 AI 数据中心,也需要卡车全天持续不断地进行配送。
Delivering compressed natural gas via truck is not easy nor cheap. When including the cost of labor, specialized equipment and fuel to move the trucks themselves, the delivered cost is roughly four times the price of gas sent through a major pipeline hub, according to Jack Weixel, senior director of energy analysis at East Daley Analytics. Gas must be taken from a pipeline, compressed into a trailer, driven sometimes multiple hours to a site, and then decompressed to fill generators. Even a relatively small AI data center requires trucks making deliveries constantly throughout the day.
成本和复杂性正是压缩天然气主要被用于采矿或石油钻探等特种工业作业的原因之一,因为这些作业通常发生在远离电网连接点的偏远地区。
This cost and complexity is part of the reason why compressed gas has mostly been relegated to specialized industrial operations, such as mining or oil drilling, that take place in remote areas far from interconnection points with the electric grid.
不过,对于甲骨文(Oracle)这样的公司而言,这或许仍是最佳的权宜之计。该公司已投入数十亿美元并押上自身声誉,力求迅速向包括OpenAI在内的客户交付数据中心。目前,甲骨文的自由现金流为负,预计在其更多人工智能数据中心建成之前,这一状况将持续下去。在犹他州的项目中,甲骨文的天然气供应由Certarus提供;而在得克萨斯州,则由VoltaGrid负责。
Still, it may be the best stopgap for a company like Oracle, which has put billions of dollars and its reputation on quickly delivering data centers for customers including OpenAI. Oracle’s free cash flow is currently negative and expected to remain that way until more of its AI data centers are completed. At the Utah project, Oracle’s gas deliveries were powered by Certarus. In Texas, they are provided by VoltaGrid.
“特别感谢VoltaGrid团队找到了经济高效的供电方案,确保我们的客户能够按时使用OCI资源。”在收到关于此事的评论请求后不久,甲骨文在社交媒体上这样写道,其中OCI指的是甲骨文云基础设施(Oracle Cloud Infrastructure)。与甲骨文类似,VoltaGrid也未回应评论请求,但已在社交媒体上发布了有关此次合作的信息。
“Shoutout to the VoltaGrid team for finding cost-effective power solutions to ensure our customers can access OCI capacity on schedule,” Oracle wrote on social media shortly after receiving a request for comment on this story, referring to Oracle Cloud Infrastructure. VoltaGrid, similarly to Oracle, didn’t respond to a request for comment, but posted on social media about the partnership.
Certarus拒绝就具体交易发表评论,但表示,数据中心在接入管道和电网方面所需的时间延长,“催生了对快速部署且可扩展的能源解决方案日益增长的需求”。关键问题在于,这种解决方案能拓展到何种程度。鉴于“木星计划”(Project Jupiter)的规模,即便只为其全部容量的一小部分供电,每天也需要数十辆卡车进行运输。
Certarus declined to comment on specific deals, but said the extended timelines for data centers to secure connections with pipelines and the grid “have created a growing need for rapidly deployable and scalable energy solutions.”The big question is how far this solution can expand. Given Project Jupiter’s size, even powering a small fraction of its full capacity would require dozens of truck deliveries a day.
SemiAnalysis能源分析师Ellie Holbrook表示,如果甲骨文仅用压缩天然气(CNG)为100兆瓦的电力需求供电——这约占其最终2.45吉瓦规模的4%——那么每辆大型拖车只能提供约40分钟的电力。
If Oracle powered just 100 megawatts — about 4% of its ultimate 2.45-gigawatt footprint — with CNG deliveries, each large trailer would only provide about 40 minutes of electricity, said Ellie Holbrook, an energy analyst at SemiAnalysis.