在成功阻挠甲骨文公司在新墨西哥州的数据中心计划后,环保活动人士表示,他们现在已拥有一份蓝图,可在美国各地对超大规模数据中心运营商发起类似运动。
After successfully disrupting Oracle Corp.’s data center plans in New Mexico, environmental activists say they’ve now got a blueprint for waging similar campaigns against hyperscalers across the US.
新能源经济组织(NEE)执行董事马里埃尔·纳纳西表示,甲骨文在水资源和空气许可方面的处理方式,为环保非营利组织在法庭上挑战该公司计划打开了大门,并为其他活动人士提供了可复制的模板。
Mariel Nanasi, executive director of New Energy Economy (NEE), says Oracle’s handling of water and air permits opened the door for environmental nonprofits to challenge the company’s plans in court, and created a template for other activists to replicate.
这场斗争远未结束。10月15日,12位共和党籍州检察长要求联邦监管机构允许建设甲骨文为其数据中心供电所需的天然气管道。甲骨文也试图调整其做法以回应环保关切。但纳纳西表示,她代表的活动人士将继续战斗,直到迫使甲骨文“撤离”。该公司的挫折已在市场上引起反响。上个月曝出,甲骨文因许可障碍引发的后果而援引不可抗力条款。随后有消息称,该公司试图规避因潜在延误而产生的飙升开支,这引发了包括甲骨文在内的超大规模运营商及其供应商股价的普遍下跌。
The battle is far from over. On Oct. 15, 12 Republican state attorneys general asked federal regulators to allow construction of a gas pipeline that Oracle needs to power its data centers. And Oracle has sought to adjust its approach to address environmental concerns. But Nanasi says the activists she represents will keep fighting until Oracle is forced “to walk.”The company’s setbacks have reverberated through markets. Last month it emerged that Oracle had cited force majeure as it sought to deal with the fallout of permitting hurdles. News that it was trying to shield itself from soaring expenses tied to potential delays then triggered a broad-based slump in the shares of hyperscalers including Oracle, as well as their vendors.
纳纳西说:“我丈夫前几天指着我对一位朋友说:‘这就是不可抗力。’”甲骨文公司发言人表示,该公司依然“致力于负责任地开发朱庇特项目,并保护新墨西哥州的空气和水资源”。该公司尊重公众“提出担忧的权利,我们已通过对项目设计作出实质性改进来回应”。
“My husband said to a friend the other day, while pointing to me, ‘This is the force majeure,’” Nanasi says. A spokesperson for Oracle said the company remains “committed to developing Project Jupiter responsibly and protecting New Mexico’s air and water.”The company respects the public’s “right to raise concerns and we have responded with meaningful improvements to the project’s design.”
密歇根大学信息与公共政策助理教授本·格林表示,反对数据中心的活动人士“取得的成果远超我的预期”。结果是,地方官员和政客“现在越来越难直接无视异议者的声音”。甲骨文在新墨西哥州遭遇不可抗力时刻,此前贝莱德公司在遭遇当地激烈反对后,放弃了在弗吉尼亚州的数据中心园区项目。据由人工智能情报公司10a Labs运营的数据中心观察组织统计,今年上半年全美至少有106个服务器农场项目——涉及约1980亿美元投资——因当地反对而被叫停或推迟。
Ben Green, assistant professor of Information and Public Policy at the University of Michigan, says the activists fighting data centers “have achieved far more than I ever expected them to.”As a result, it’s now getting “harder and harder for local officials and politicians to just ignore the voices of dissenters.”Oracle’s force-majeure moment in New Mexico comes after Blackstone Inc. recently abandoned a data center campus in Virginia amid fierce local backlash. Across the US, at least 106 server-farm projects — representing about $198 billion in investments — were blocked or delayed amid local opposition during the first half of this year, according to Data Center Watch, a monitor run by AI intelligence firm 10a Labs.
马萨诸塞大学阿默斯特分校9月的一项民调显示,65%的美国选民反对在当地建设人工智能数据中心,仅11%表示支持。投资者表示,市场影响如今已大到不容忽视。
A September poll by University of Massachusetts Amherst puts US voter opposition to local AI data centers at 65%, compared with just 11% in favor. Investors say the market implications are now too big to disregard.
EQT AB美洲基础设施主管亚历克斯·达登表示,这“正成为一个更重要的因素”。他称,在EQT做出投资前,必须考察“社区如何看待该开发项目”。环保运动加剧了日益笼罩人工智能行业的普遍不安感。除了担心这项新兴技术可能扼杀就业、冲击社会外,市场还因人工智能债务驱动的增长假设而定期出现恐慌。
It’s “becoming a bigger factor,” says Alex Darden, head of infrastructure for the Americas at private equity firm EQT AB. He says that before EQT makes an investment, it has to look at “how the community views that development.”Environmental campaigns are adding to the general sense of unease that increasingly hangs over the AI industry. Aside from fears that the nascent technology may kill jobs and disrupt societies, there are regular bouts of market panic over AI’s debt-fueled growth assumptions.
本月初,亿万富翁雷·达里奥将人工智能描述为即将破裂的“经典泡沫”,进一步助长了此类担忧。
Earlier this month, billionaire Ray Dalio fanned such concerns when he described AI as a “classic bubble” that’s nearing a bursting point.
生物多样性中心(CBD)的宪法权利律师盖尔·埃文斯(Gail Evans)——另一个在新墨西哥州反对甲骨文数据中心计划的非营利组织——表示,她对来自“两党人士”的支持力度感到震惊。她说,非营利组织为本已强大的草根政治运动增添了法律专业知识。
Gail Evans, a constitutional rights attorney with the Center for Biological Diversity (CBD) — another nonprofit fighting Oracle’s data center plans in New Mexico — says she’s been struck by the amount of support from “people on both sides of the aisle.”She says the nonprofits add legal knowhow to what’s already a powerful grassroots political movement.

NEE和CBD的资金来源均为慈善组织和个人捐赠者,在发现甲骨文在环境许可方面走捷径后,两组织均在法庭上取得了胜利。
Both NEE and CBD, which get their financial backing from charitable organizations and individual donors, have had success in the courts after catching shortcuts they say Oracle took in its approach to environmental permitting.
“我们不会因为资金耗尽而停止对抗‘朱庇特项目’,”纳纳西(Nanasi)说。“我们打算坚持到底。”
“We are not going to run out of money to fight Project Jupiter,” says Nanasi. “We intend to see this through.”
尽管如此,对抗资金雄厚的超大规模云服务商仍需勇气,埃文斯将其形容为“大卫对战歌利亚式的较量”。
Still, taking on deep-pocketed hyperscalers takes some gumption, with Evans describing it as “a David-versus-Goliath kind of battle.”
加州大学洛杉矶分校政治学家梅根·穆林(Megan Mullin)表示,采用NEE和CBD创建的这套策略“代价高昂”。“这需要大量信息、大量法律专业知识,以及反对项目的团体具备极高的能力,以便看到并介入所有不同的决策节点。”
Megan Mullin, a political scientist at the University of California, Los Angeles, says using the playbook created by NEE and CBD “is costly.”“It takes a lot of information. It takes a lot of legal expertise. And it takes high capacity for the groups that are opposing the project to see and access all the different decision points,” she says.
细节方面:8月,新墨西哥州最高法院暂停了甲骨文公司计划中的朱庇特数据库园区所需燃气发电许可。在活动人士提出公众审查不足的担忧后,法院还暂时禁止使用一口淡水井。此外,该州土地办公室拒绝为计划中的燃气管道提供公共土地通行权。随后,朱庇特项目赢得法院裁决,允许许可流程恢复。10月15日,由西弗吉尼亚州牵头的12个共和党州的12位总检察长组成的联盟,请求联邦能源监管委员会批准该管道建设,理由是更广泛的环境审查会使全国类似项目变得复杂。
The details:In August, the New Mexico Supreme Court put on hold a permit for the gas-powered electricity needed for Oracle’s planned Jupiter data base campus. It also blocked — albeit temporarily — the use of a freshwater well after activists raised concerns about inadequate public scrutiny. Separately, the state’s land office denied access to public lands for a planned gas pipeline. Project Jupiter then won a court ruling allowing the permitting process to resume. And on Oct. 15, a coalition of 12 AGs from 12 Republican states led by West Virginia asked the Federal Energy Regulation Commission to authorize construction of the pipeline, arguing that a broader environmental review would complicate similar projects across the country.
10月16日,甲骨文提交了其燃料电池微电网方案的修改,称这将减少排放。此举是回应新墨西哥州环境部空气质量局的要求。目前,甲骨文仍未获得使用燃气发电计划所需的空气质量许可。燃气管道则在等待联邦能源监管委员会的决定,预计最早于12月初做出裁决。
On Oct. 16, Oracle put forward an alteration to its proposal for a fuel cell microgrid it says will cut emissions. The move was in response to a request from the New Mexico Environment Department’s Air Quality Bureau. For now, Oracle still doesn’t have an air-quality permit for its plan to use gas-powered electricity. And the gas pipeline is awaiting a decision by FERC, which is expected by early December.
生物多样性中心高级律师科林·考克斯表示,甲骨文专注于所谓的“上电速度”——即数据中心开发商能多快获得足够电力使设施投入运行——导致其在某些程序步骤上操之过急,从而暴露在法律挑战之下。
Colin Cox, a senior attorney at CBD, says Oracle’s focus on so-called speed to power — or how quickly a data center developer can secure enough electricity to get a facility up and running — has led it to rush some procedural steps in a way that’s opened it up to legal challenges.
“我们的目标并非刻意要拖延项目的进展;我们的目标是保护环境,”考克斯说道,“但他们严重违反了我们的环保法规——无论他们这样做是出于故意还是无心。”
“It’s not that our goal was to slow this down necessarily; our goal is to protect the environment,” Cox said. “But they’ve done such a bad job complying with our environmental laws, whether that’s intentional or not.”
他指出,甲骨文(Oracle)常常在未获得所有必要许可的情况下就开始建设数据中心。他说:“‘朱庇特项目’(Project Jupiter)最显著的特点就是他们急于推进项目的实施速度,这种做法非常草率。”
He says Oracle has tended to start construction on parts of the campus without all the necessary permits. “One of the defining features of the Project Jupiter has been the speed with which they’re trying to ram this through,” he says. “It’s sloppy.”
针对一系列问题,甲骨文通过电子邮件回应称:“我们将继续倾听各方意见、分享相关信息,并与当地社区合作,共同打造一个对新墨西哥州南部有益的项目。”这些环保运动主要依赖于州政府的法律法规。而在联邦层面,唐纳德·特朗普总统将数据中心视为创造就业机会、促进投资、推动经济增长和增加税收的重要手段;他还表示美国必须在人工智能领域超越中国。
As part of a detailed list of responses to questions that included references to previously announced measures, Oracle said by email that it “will continue listening, sharing information and working with the community to deliver a responsible project for southern New Mexico.”The environmental campaigns rely heavily on state laws. At the federal level, meanwhile, President Donald Trump has described data centers as a source of jobs, investment, economic growth and tax revenue. He also says the US needs to win the AI race against China.
不过,特朗普声称那些建设数据中心的公司已承诺承担相关电力费用及基础设施建设的成本,以减轻消费者的负担。不过批评者指出,特朗普的这一承诺其实并不具有法律约束力。
And according to Trump, the companies behind AI data centers have committed to covering the costs of electricity and related infrastructure needed to power their facilities, to protect consumers from rising utility bills. Critics have pointed out that the commitment touted by Trump is non-binding.

对于环保活动人士来说,计划建设的AI数据中心项目数量众多,且仍在不断增加:在宾夕法尼亚州,亚马逊(Amazon.com)旗下的AWS公司在扩大其数据中心规模时遭到了包括“塞拉俱乐部”(Sierra Club)和“清洁空气委员会”(Clean Air Council)在内的环保组织的反对;在密西西比州,埃隆·马斯克(Elon Musk)的xAI公司计划建设的“Colossus 2”数据中心项目遭到了“地球正义组织”(Earthjustice)、“南方环境法律中心”(Southern Environmental Law Center)以及“全国有色人种促进协会”(National Association for the Advancement of Colored People)的反对;在明尼苏达州,谷歌(Google,隶属于Alphabet公司)的数据中心建设计划也引发了当地环保人士的抵制。
For environmental activists, the list of planned AI data center campuses being targeted is long and growing. In Pennsylvania, Amazon.com Inc.’s AWS faces pushback from environmental groups including Sierra Club and Clean Air Council as the company expands its data center footprint there.
谷歌的一位发言人拒绝置评;亚马逊和 xAI 的发言人也没有回应记者的评论请求。
In Mississippi, the Colossus 2 site planned by Elon Musk’s xAI faces opposition from Earthjustice, Southern Environmental Law Center and the National Association for the Advancement of Colored People.
目前美国正在建设中的大多数数据中心都依赖天然气作为能源。彭博新能源财经(BloombergNEF)警告称,这一行业有可能“阻碍美国在气候保护方面的进展”。BNEF 在 6 月份发布的一份分析报告显示,美国的数据中心开发商已经宣布了总计 124 吉瓦的天然气供应能力。
Efforts by Alphabet Inc.’s Google to build data centers in Minnesota are in the crosshairs of local environmental activists. A spokesperson for Google declined to comment. Spokespeople at Amazon and xAI didn’t respond to requests for comment.
来自芝加哥商业区(CBD)的埃文斯(Evans)指出,早期人们对人工智能(AI)的 enthusiasm 主要基于这样一个假设:AI 将有助于推动对可再生能源的需求。但她表示:“然而,从当前美国的数据中心发展情况来看,这些数据中心仍然依赖化石燃料作为能源。”
Most US data centers in the development pipeline rely on natural gas for power, with BloombergNEF warning that the sector has the potential “to derail climate progress in the US.”A June analysis by BNEF showed that US data center developers had already announced as much as 124 gigawatts of on-site gas capacity. Evans from CBD says much of the early enthusiasm associated with AI has been tied to an assumption that it would help drive demand for renewables.

密歇根大学的格林(Green)认为,这些担忧如今已经成为了大型数据中心运营商(即所谓的“超大规模数据中心运营商”)面临的全国性难题。
But “when you look at the type of development that’s happening in this country, and right now, it’s data centers and it’s fossil-fuel-powered data centers,” she says.
这已经演变成了一场“更大的政治运动”(即一场涉及广泛社会议题的政治运动)。
Green at the University of Michigan says those concerns are now morphing into a nationwide headache for hyperscalers. It’s become a “larger political movement.”