大型科技企业与阿博特如何让德克萨斯州成为数据中心“震中”共和党籍州长格雷格·阿博特(Greg Abbott)近期对数据中心态度强硬,但记录和采访显示,不到一年前,他的办公室和任命的官员还在与科技及电力行业密切合作,积极引进相关项目。发布时间:2026-10-27T09:00:00Z一块批评阿博特州长将数据中心引入巴斯特罗普县(Bastrop County)作用的广告牌,于9月18日矗立在雪松溪(Cedar Creek)的21号州道旁。
How Big Tech and Abbott made Texas the ‘epicenter’ of data centers As Republican Gov. Greg Abbott talks tough on data centers, records and interviews show how his office and appointees worked closely with the tech and power industries. Published: 2026-10-27T09:00:00Z A billboard criticizing Gov. Greg Abbott’s role in bringing data centers to Bastrop County is seen along State Highway 21 in Cedar Creek on Sept. 18.
休斯顿——德克萨斯州共和党籍州长格雷格·阿博特已对数据中心“打压”数月,但不到一年前,其任命的官员和幕僚还在积极设法将此类项目引入该州。
HOUSTON — Texas Republican Gov. Greg Abbott has been cracking down on data centers for months, but less than a year ago his appointees and staffers were actively trying to bring projects to the state.
根据《政治》(POLITICO)获得的记录,2025年12月16日,即德克萨斯州宣布全面变革以加快数据中心接入电网的两天前,阿博特的核心幕僚与该州最大的科技和输电公司代表举行了一次闭门会议。
On Dec. 16, 2025, two days before Texas announced sweeping changes to expedite grid access to data centers, Abbott’s top staff held a closed-door meeting with representatives of the state’s largest tech and transmission companies, according to records obtained by POLITICO.
文件显示,谷歌(Google)、OpenAI、Meta、亚马逊云科技(Amazon Web Services)和英伟达(Nvidia)的代表获确认将与阿博特团队会面,德克萨斯州首席电力监管官和电网管理者也将出席,共同探讨建设该州电网事宜。记录还显示,该州四大主要输电公司——安科电力(Oncor Electric)、中心点能源(CenterPoint Energy)、AEP德克萨斯(AEP Texas)和德克萨斯-新墨西哥电力(Texas-New Mexico Power)的官员也在场。
The documents show representatives from Google, OpenAI, Meta, Amazon Web Services and Nvidia were “confirmed” to meet with Abbott’s team, joined by Texas’ head electricity regulator and grid manager to discuss building out the state’s power grid. Also in the room, according to the records: officials with the state’s four main electric transmission companies— Oncor Electric, CenterPoint Energy, AEP Texas and Texas-New Mexico Power.
一位获准匿名发言的与会者表示,阿博特办公室传递的信息很明确:我们希望数据中心来德克萨斯州,并希望与业界合作,清除障碍以促成此事。
A person at the meeting, who was granted anonymity to speak freely about what happened, said the message from Abbott’s office was clear: We want data centers to come to Texas, and we want to work with the industry to remove roadblocks to make that happen.
该人士说:“那次会议的要点实际上是说,‘我们致力于解决这个问题,并寻找一条更好的前进道路。’”这条道路于2025年12月18日由电网官员在州公用事业监管机构的公开会议上铺陈出来——该框架在很大程度上类似于谷歌和一家总部位于德克萨斯州的超大规模数据中心运营商提出的方案。
“The point of that meeting really was to say, ‘We’re committed to fixing this and finding a better path forward,’” the person said. That path was laid out by grid officials to the state’s utility regulators at an open meeting Dec. 18, 2025 — a framework that was largely similar to one proposed by Google and a Texas-based hyperscaler.
在随后的几个月里,得克萨斯州电力可靠性委员会(ERCOT)和州公用事业委员会一直在努力制定新规则,并开发新的流程,将大型电力用户——几乎全部是数据中心——接入该州的主要电网。这些举措发生之际,特朗普政府鼓励得克萨斯州领导人支持数据中心发展以及人工智能的扩张。
In the months that followed, the Electric Reliability Council of Texas and the state Public Utility Commission worked to write new rules and develop the new process to bring large power users — almost all of which are data centers — onto the state’s main power grid. The moves came as the Trump administration encouraged Texas leaders to support data center development and the growth of artificial intelligence.
但这一势头随着夏季推进而骤然停滞,数据中心在得克萨斯州乃至全美变得深受欢迎,而阿博特正面临其政治生涯中最艰难的连任竞选。
But that momentum came to an abrupt halt as summer progressed and data centers became deeply unpopular in Texas and across the country , and as Abbott faces the most difficult reelection bid of his political career.
阿博特于6月呼吁公用事业委员会和电网管理者对数据中心加以限制,当时愤怒的居民在州各地的市政厅中呼吁实施数据中心暂停令,并推动赋予地方政府更多监管权。
Abbott called on the PUC and the grid manager to clamp down on data centers in June as angry residents filled town halls across the state, calling for data center moratoriums and laws to give local governments more authority to regulate them.
在为期15小时的州参议院委员会听证会结束后不到一周,数百名愤怒的选民在会上痛批该州未能采取更多措施遏制数据中心的扩张,并提出了765千伏输电线路等方案。随后,阿博特于8月初下令公用事业委员会和ERCOT暂停数据中心电网接入审批。
Less than a week after a 15-hour long state Senate committee hearing saw hundreds of furious constituents roast the state for not doing more to slow the proliferation of data centers and proposed 765-kilovolt transmission lines, Abbott in early August ordered the PUC and ERCOT to pause data center grid connection approvals.
这些举措与当年11月阿博特与谷歌、Alphabet首席执行官桑达尔·皮查伊举行联合新闻发布会时称得克萨斯州为“AI发展中心”的说法形成了鲜明对比。
Those actions are a reversal from when Abbott called Texas the “epicenter” of AI development in a joint press conference with Google and Alphabet CEO Sundar Pichai in November 2025.
阿博特新闻秘书安德鲁·马哈勒里斯上周在一份声明中表示,其团队与数据中心开发商于2025年12月举行的会议旨在传递一个明确信息:“数据中心必须立即做出改变,把得克萨斯居民和社区放在首位。”
Abbott press secretary Andrew Mahaleris said in a statement last week that the December 2025 meeting between his staff and data center developers was meant to send a clear message: “Data centers must make immediate changes and put Texas residents and communities first.”
“随着得克萨斯人对这些项目的担忧日益增长,州长阿博特采取了果断行动,设定了明确的护栏来保护得克萨斯人,”马哈勒尔斯说。
“As Texans’ concerns with these projects grew, Governor Abbott took decisive action to set clear guardrails that protect Texans,” Mahaleris said.
尽管如此,到2032年某个时候,可能会有超过360个新的数据中心项目投入运营——这将使该州运营中的科技园区数量翻倍,并使得德克萨斯州成为全球数据中心之都。而该州正在努力敲定一项价值330亿美元的超高压输电项目,该项目将有助于从东德克萨斯向二叠纪盆地腹地的科技园区供电。
Still, more than 360 new data center projects could come online by sometime in 2032 — doubling the number of the tech campuses operating in the state and making Texas the global capital of data centers. And the state is working to finalize a $33 billion, ultra-high voltage transmission project that would help power the tech campuses from East Texas to the heart of the Permian Basin.
正在挑战阿博特的民主党籍州众议员吉娜·伊诺霍萨在一份声明中表示,在接受了这些数据中心首席执行官的竞选捐款后,州长邀请数据中心来到德克萨斯州,并加快了它们的审批流程。
Democratic state Rep. Gina Hinojosa, who is challenging Abbott, said in a statement that the governor invited the data centers to Texas and fast-tracked their approvals after taking campaign contributions from their CEOs.
伊诺霍萨说:“这就是格雷格·阿博特治下的德克萨斯州的腐败现实:在关起门来的房间里,他与数据中心高管达成交易,丝毫不为德克萨斯人着想。”商业会议虽然州长必须在无数问题上表态,但阿博特的幕僚团队却深耕电力行业。
“This is the corrupt reality of Greg Abbott’s Texas: behind closed doors, he makes deals with data center executives without thinking twice about Texans,” Hinojosa said. Business meeting While governors must take positions on countless issues, Abbott’s staff is steeped in the power industry.
幕僚长罗伯特·布莱克曾担任德州电力可靠性委员会(ERCOT)公共事务副总裁,以及AEP德克萨斯公司对外事务副总裁。
Chief of staff Robert Black formerly served as vice president of public affairs for ERCOT and was vice president of external affairs for AEP Texas.
预算主任费舍尔·雷诺兹四世此前曾担任下科罗拉多河管理局(LCRA)幕僚长,该机构是一个非营利性政治分区,也从事输电建设。
Budget director Fisher Reynolds IV previously was chief of staff of the Lower Colorado River Authority, a nonprofit political subdivision that also builds transmission.
布莱克的Outlook日历记录——通过公开记录请求获得——显示,他、雷诺兹、副幕僚长托比·贝克、政策主任科里·菲什和政策顾问杰奎琳·希尔被安排于2025年12月16日参加会议。
Black’s Outlook calendar records — obtained through an open records request — show that he, Reynolds, deputy chief of staff Toby Baker, policy director Cory Fish and policy adviser Jacquelyn Hill were scheduled to attend the meeting on Dec. 16, 2025.
记录显示,确认出席者名单上还包括德克萨斯州州务卿罗伯特·豪登、公用事业委员会(PUC)主席托马斯·格利森及其幕僚长,以及PUC副执行董事巴克斯代尔·英格利希。ERCOT首席执行官帕布洛·维加斯和其他三位ERCOT高层官员,以及麦肯锡公司的两名顾问也在名单上。阿博特任命了豪登和格利森,而PUC负责监管ERCOT。
Also on the list of confirmed attendees, the records show, were Texas Secretary of State Robert Howden, PUC Chair Thomas Gleeson and his chief of staff as well as PUC deputy executive director Barksdale English. ERCOT CEO Pablo Vegas and three other top ERCOT officials, plus two consultants from McKinsey & Co., were also on the list. Abbott appointed both Howden and Gleeson, and the PUC oversees ERCOT.
值得注意的是,出席者名单中没有任何来自公共事务顾问办公室的官员,该州机构的职责是代表居民和小企业电费用户的利益。布莱克的日程表将此次会议称为“输电圆桌会议”。
Notably absent from the list of attendees were any officials from the Office of the Public Utility Counsel, a state agency tasked with representing residential and small business ratepayers’ interests. Black’s calendar called the meeting a “transmission roundtable.”
公共事务委员会未回复多次置评请求。得州电力可靠性委员会和公共事务顾问办公室均拒绝就此事置评。
The PUC did not respond to multiple requests for comment. ERCOT and the Office of Public Utility Counsel declined to comment for this story.
当被问及2025年12月16日的会议时,AEP Texas和Meta的官员表示,名单上列出的与会员工已不在各自公司任职。Oncor发言人凯里·邓恩证实,该公司监管事务副总裁出席了会议。
When asked about the Dec. 16, 2025, meeting, officials with AEP Texas and Meta said the employees listed as attending were no longer with their companies. Kerri Dunn, a spokesperson for Oncor, confirmed the company’s vice president of regulatory affairs attended.
邓恩通过电子邮件表示:“我们的团队成员定期与各类利益相关者会面,包括州和地方官员、监管机构、客户及其他人员,这是我们持续为得州民众提供安全可靠电力服务努力的一部分。”
“Our team members regularly meet with a variety of stakeholders, including state and local officials, regulators, customers, and others, as part of our efforts to continue providing safe and reliable electric service to Texans,” Dunn said via email.
文件并未显示阿博特本人出席了会议。他的办公室未回复关于州长是否出席或是否知情会议的具体提问。
The document does not say Abbott himself was at the meeting. His office did not respond to specific questions asking whether the governor was there or if he knew about the meeting.
一位出席会议并随后向《政治报》透露情况的人士表示,来自公共事务委员会、得州电力可靠性委员会和阿博特办公室的官员试图让数据中心和其他大型用电户放心。
The person who attended the meeting and later spoke with POLITICO said officials from the PUC, ERCOT and Abbott’s office sought to reassure data centers and other large electricity users.
开发商们对项目因得州电力可靠性委员会研究如何将其接入电网的流程而延误感到日益焦虑。延误如此普遍,以至于一些开发商担心州政府试图阻止他们并网,该人士称。
Developers had been growing anxious about projects that were being delayed by ERCOT’s process of studying how to bring them onto the grid. The delays were so common that some developers worried the state was trying to prevent them from coming online, the person said.
该人士回忆道:“信息基本上是‘我们知道有传言说要暂停大型负荷并网——那不是正在发生的事。我们之前的流程行不通,我们正在制定一个行之有效的解决方案。’”知情人士称,一些未出现在布莱克日程表上的人员也参加了会议,其中包括得克萨斯州石油天然气协会和得克萨斯州化学委员会的代表。这两个组织均未回应置评请求。
“The messaging was basically ‘We know there’s this rumor about a moratorium to interconnect large loads — that’s not what is happening. Our prior processes don’t work, and we’re coming up with a solution that works,’” the person recalled. The person said some people not listed on Black’s calendar also attended the meeting, including representatives from the Texas Oil & Gas Association and the Texas Chemistry Council. Neither organization responded to a request for comment.
两天后,即2025年12月18日,维加斯在公用事业委员会的公开会议上发言,公布了该州将大型用电户(几乎全是数据中心)接入电网方式的彻底变革。
Two days later, on Dec. 18, 2025, Vegas spoke at a PUC open meeting and unveiled a wholesale overhaul of how the state would look to bring large power users — almost all of which are data centers — onto the grid.
维加斯表示,ERCOT此前是逐个研究项目,这导致一旦另一个项目寻求在附近并网,就必须持续重新研究拟建项目。这造成了让大型用电户接入电网的延误。
ERCOT had been studying the projects one at a time, Vegas said, and that had created issues where they would have to continuously restudy proposed projects as soon as another project sought to come online nearby. That resulted in delays in enabling the large power users to plug into the grid.
维加斯在公用事业委员会会议上表示,取而代之的是,ERCOT将成组研究数据中心和大负荷,批量授予它们并网许可。他说,ERCOT将在2026年第一季度内敲定首批此类群组(称为“第零批次”)的并网流程。
Instead, Vegas said at the PUC meeting, ERCOT would study data centers and large loads in groups, granting them all permission to come online in batches. He said ERCOT would finalize a process for bringing the first of those groups, known as Batch Zero, within the first quarter of 2026.
维加斯说:“我们认为时机是这件事非常重要的一部分。显然,存在着快速行动的压力,以支持即将到来的经济增长。”
“We think timing is a really important part of this,” Vegas said. “There’s clearly a pressure to move quickly to support the economic growth that’s coming our way.”
维加斯勾勒的总体框架,与谷歌和得克萨斯州大规模数据中心运营商Lancium当天联合提交的一份提案有几个关键相似之处,其中包括财务承诺要求、将“大负荷”定义为耗电量在75兆瓦及以上、以及成组而非逐个研究数据中心项目。
The general framework laid out by Vegas bore several key similarities to a joint proposal filed by Google and Texas-based hyperscaler Lancium the same day, which included financial commitment requirements, classifying “large loads” as consuming 75 megawatts and up, and studying data center projects in groups rather than one at a time.
谷歌和Lancium均拒绝就此事置评。与谷歌不同,Lancium未被列为2025年12月16日会议的参与者之一。
Google and Lancium declined to comment for this story. Unlike Google, Lancium was not listed as one of the participants at the Dec. 16, 2025, meeting.
维加斯表示,“第零批次”将获得ERCOT电网从现在到2032年存在的所有备用电力。其余批次将随着全州输电网络的建设获得更多电力,以试图跟上需求。
Vegas has said Batch Zero will be granted all the spare power that exists on ERCOT’s grid between now and 2032. The rest would be granted more power as more transmission was built statewide to try to keep up with the demand.
预计这种电力需求的增加将使该州的输电垄断企业受益,这些企业为其建设的、用于服务大型负荷和全州其他地区的电线杆和电线获得保证的回报率。
That increased power demand is expected to be a boon for the state’s transmission monopolies, which earn a guaranteed rate of return for the electric poles and wires they build to serve large loads and the rest of the state.
此外,得益于2023年的一项法律,ERCOT(德克萨斯州电力可靠性委员会)现在必须使用输电公司的需求预测来规划电网建设,而不再依赖这家非营利电网管理机构内部的预测。
And thanks to a 2023 law, ERCOT is now required to use the transmission companies’ demand forecasts for planning grid build-outs, rather than relying on the nonprofit grid manager’s in-house forecasts.
德克萨斯州电力公司协会(该州电力公司的行业团体)未回应置评请求。白宫之行在Vegas(维加斯公司)于12月宣布计划变更后,ERCOT看到来自大型电力用户的互联申请激增,从2025年第四季度的48吉瓦飙升至2026年第一季度的198吉瓦。
The Association of Electric Companies of Texas, a trade group for power companies in the state, did not respond to a request for comment. White House visit After Vegas announced planned changes in December, ERCOT saw interconnection requests from large power users skyrocket from 48 gigawatts in the fourth quarter of 2025 to 198 GW just in the first quarter of 2026.
相比之下,ERCOT的历史最高电力需求纪录约为91吉瓦,于7月22日创下。
By comparison, the all-time power demand record for ERCOT is roughly 91 GW, logged on July 22 .
这股兴趣热潮不仅引起了德克萨斯州监管机构的注意,还传到了华盛顿。
That wave of interest didn’t just catch the eye of Texas regulators — it made its way up to Washington.
当特朗普政府于3月邀请100多名共和党州议员访问白宫时,商务部长霍华德·卢特尼克和前国家能源主导委员会电力资深主任彼得·莱克告诉他们,需要支持数据中心落户德克萨斯州,共和党州众议员韦斯·维德尔和布拉德·巴克利在接受《政治客》采访时分别表示。
When the Trump administration invited more than 100 Republican state lawmakers to the White House in March, Commerce Secretary Howard Lutnick and former National Energy Dominance Council senior director for power Peter Lake told them they needed to support the data centers coming to Texas, Republican state Reps. Wes Virdell and Brad Buckley told POLITICO in separate interviews.
莱克曾于2021年4月至2023年6月担任德克萨斯州公用事业委员会主席。
Lake also served as chair of the PUC of Texas from April 2021 until June 2023.
巴克利表示,卢特尼克和莱克强调了白宫的观点,即数据中心对于帮助美国在人工智能军备竞赛中击败中国至关重要,建设数据中心符合国家安全利益。
Buckley said Lutnick and Lake underscored the White House’s message that data centers were necessary to help the U.S. defeat China in the AI arms race, and that building them out was in the interest of natural security.
“彼得·莱克进来告诉我们,我们需要支持德克萨斯州的数据中心。这让我大吃一惊,”维德尔在采访中说。“我后来对卢特尼克提到,我说你们知道他们正在住宅旁边建设吗?他说,‘哦,是的,我听说了’,然后就想换个话题。”商务部未回应关于此次会议的置评请求。
“Peter Lake came in telling us we need to get on board with the data centers in Texas. I was shocked by all of that,” Virdell said in an interview. “I mentioned to Lutnick after this, I said you understand they’re building next to residential homes? He said, ‘Oh yeah, I heard that,’ and then wanted to move on.”The Commerce Department did not respond to a request for comment on the meeting.
莱克在一份声明中表示,为数据中心供电“对美国的经济和国家安全至关重要”。他说,像“费率支付人保护承诺”这样的行动为负责任的开发设定了国家标准。
In a statement, Lake said powering data centers is “critical to America’s economic and national security.”He said actions like the Ratepayer Protection Pledge set a national standard for responsible development.
白宫发言人莉兹·哈斯顿在一份声明中表示,唐纳德·特朗普总统专注于将数据中心打造为全国各地社区的“增长和机遇引擎”,同时巩固美国在人工智能竞赛中对中国的“统治地位”。
White House spokesperson Liz Huston said in a statement that President Donald Trump is focused on turning data centers into “engines of growth and opportunity” for communities across the country while cementing U.S. “dominance over China” in the AI race.
极光能源研究公司的研究负责人安妮·刘表示,数据中心开发商可能在今年第一季度出于多种原因涌向得克萨斯州,其中包括渴望参与“零批次”研究。
Data center developers may have begun flocking to Texas in the first quarter of this year for several reasons including an eagerness to participate in Batch Zero, said Anne Liu, a research lead with Aurora Energy Research.
刘说:“对于关注ERCOT(得克萨斯电力可靠性委员会)的人来说,一个吸引点在于它比其他电力市场更早地实现了有序化。而ERCOT做得越多,给想要接入电网的数据中心带来的好处就越大。”
“One of the attractive points for people looking at ERCOT is that it was so organized much earlier than the other [electricity] markets,” Liu said. “And the more ERCOT does, the more benefit it gives to the data centers that want to get connected.”
刘表示,批次研究流程和“零批次”给数据中心开发商带来的确定性,比他们在其他电力市场所拥有的更多,因为在其他市场,监管机构在起草将项目上线的流程和规则方面取得的进展较少。
The batch study process and Batch Zero gave data center developers more certainty than they had in other power markets, Liu said, where regulators had made less progress in drafting processes and rules to bring projects online.
最终,ERCOT的大负荷互联排队容量达到470吉瓦以上,其中90%由数据中心需求构成。
Eventually, ERCOT’s large load interconnection queue reached over 470 GW, 90% of which was made up of data center demand.
2021年8月,时任得克萨斯州公用事业委员会主席的彼得·莱克在接受采访时留影。
Peter Lake, then-chair of the Public Utility Commission of Texas, sits for a portrait during an interview in August 2021.
到3月时,维德尔、巴克利和其他农村州议员已经收到大量愤怒选民的投诉,他们表示数据中心正在其选区各处涌现,而地方政府几乎没有能力对其进行监管。
By March, Virdell, Buckley and other rural state lawmakers were already getting an earful from upset constituents who said data centers were popping up across their districts, and that local authorities had little ability to regulate them.
得克萨斯州法律在很大程度上禁止城市和县制定超越州法律的地方条例,并禁止它们通过暂停令来叫停数据中心和其他类型的开发。
Texas laws largely prevent cities and counties from creating local ordinances that overstep state laws and prevent them from passing moratoriums on data centers and other sorts of development.
在缺乏主要的地方限制,尤其是在未建制县的情况下,沮丧的居民将关注焦点从地方民选官员转移到了州政府。
Without major local restrictions, especially in unincorporated counties, frustrated residents turned their attention from local elected officials to the state.
7月29日,州参议院商务委员会就数据中心和一项拟议的330亿美元输电计划举行听证会,持续了15个小时,其中大部分时间由愤怒的农村土地所有者主导,他们对数据中心以及最终将为其服务的765千伏输电线路表示不满。
A state Senate Business and Commerce Committee hearing about data centers and a proposed $33 billion transmission program lasted 15 hours on July 29 , most of which was dominated by rural landowners fuming over data centers and the 765-kV transmission lines that would ultimately help serve them.
不到一周后,阿博特下令公共事业委员会(PUC)和德克萨斯电力可靠性委员会(ERCOT)暂停数据中心电网接入审批,直到这两个机构能够对拟议项目进行审计。
Less than a week after that hearing, Abbott ordered the PUC and ERCOT to pause data center grid connection approvals until the two agencies could conduct an audit of the proposed projects.
9月,他下令德克萨斯水资源开发委员会强制数据中心报告其用水情况,并下令德克萨斯环境质量委员会(TCEQ)停止向数据中心发放许可,直到ERCOT和PUC完成审计。
In September, he ordered the Texas Water Development Board to compel data centers to report their water usage and ordered the TCEQ to stop giving data centers permits until ERCOT and the PUC could finish their audit.
预计该审计将于12月10日完成,即中期选举后一个多月。德克萨斯州立法机构常规会议将于1月开始,预计立法者将针对数据中心的税收激励措施及其运营相关规则采取行动。
That audit is expected to be finished by Dec. 10, a little more than a month after the midterm elections. The Texas Legislature’s regular session starts in January, and lawmakers are expected to take aim at tax incentives for data centers and rules around their operations.
但即使阿博特采取了针对数据中心的行动,开发商和科技公司仍继续支持他。
But even as Abbott has taken actions against data centers, developers and tech companies have continued to support him.
《德克萨斯论坛报》(Texas Tribune)对竞选捐款的分析发现,自2025年7月以来,阿博特从与数据中心有“直接联系”的捐赠者(如公司首席执行官或其员工)那里筹集了约490万美元。此外,该媒体追踪到来自与数据中心有间接联系的人士(如投资数据中心公司的人)的410万美元捐款。
A Texas Tribune analysis of campaign contributions found Abbott has raised about $4.9 million from donors with “direct ties” to data centers like company CEOs or their employees since July 2025. In addition, the outlet tracked $4.1 million in donations from people with indirect ties to data centers, like those that invest in data center companies.
《论坛报》发现,在直接和间接的数据中心相关捐款中,约280万美元是在阿博特宣布暂停数据中心审批后到账的。与此同时,这家非营利新闻机构发现,民主党对手伊诺霍萨(Hinojosa)自2025年7月以来仅记录了一笔2.5万美元的数据中心相关捐款。
About $2.8 million of the direct and indirect data center-related donations came after Abbott announced his data center pause, the Tribune found. Meanwhile, the nonprofit newsroom found Democratic rival Hinojosa logged one data center-related donation of $25,000 since July 2025.
阿博特竞选团队新闻秘书爱德华多·莱尔称《论坛报》的报道是“一个不诚实的尝试,试图利用并非新鲜的信息制造争议”。他指出阿博特的暂停令以及他呼吁结束数据中心“过时”税收优惠的做法,作为阿博特立场的证据。
Eduardo Leal, press secretary for Abbott’s campaign, called the Tribune’s report “a disingenuous attempt to manufacture controversy out of information that is not new.”He pointed to Abbott’s pause and his calls for ending “outdated” tax incentives for data centers as evidence of his stance.
莱尔说:“数据中心必须自负盈亏,保护德克萨斯州电网,自带水源,且不得干扰其运营所在的社区。”伊诺霍萨在一份声明中表示,阿博特的暂停令是一场闹剧。
“Data centers must pay their own way, protect Texas’ electric grid, bring their own water, and not disturb the communities where they operate,” Leal said. Hinojosa said in a statement that Abbott’s pause is a farce.
她说:“数据中心审批将在12月恢复运行,因为阿博特是由全球数据中心公司买通并付费的。”
“Data center approvals will be back up and running in December, because Abbott is bought and paid for by global data center corporations,” she said.
阿博特最近的行动可能并未影响维德尔选区等德克萨斯州农村地区的选民。
Abbott’s recent actions may not have swayed voters in rural Texas in areas like Virdell’s district.
这位州议员表示,一年前他曾告诉阿博特的幕僚长和其他议员,他所在的希尔地区农村选区的民众正因数据中心和765千伏输电线路而反对州政府的共和党领导层。
The state lawmaker said he told Abbott’s chief of staff and other lawmakers a year ago that folks in his rural Hill Country district were turning on the state’s Republican leadership over data centers and 765-kV transmission lines.
维德尔上周表示:“我认为阿博特大概在我告诉他他在希尔地区因这些事情而失去支持后五到六个月,看到了民调,才改变了调子。向领导层提供常识,却被完全无视,直到民调证明我是对的,这让人非常沮丧。”阅读Politico原文
“I think Abbott, once he saw the polling roughly five to six months after I told him he’s losing support in Hill Country over this stuff, he changed his tune,” Virdell said last week. “It’s very frustrating to give common sense to the folks in leadership, and for it to be completely ignored until polling shows I was correct.”Read the original article on Politico