美国最大的电网运营商计划于3月举行一场特别拍卖,以确保为数据中心需求提供新的发电容量,前提是联邦监管机构批准关于由谁买单的修订规则。
America’s largest grid operator plans a special March auction to secure new generating capacity for data-center demand if federal regulators approve revised rules governing who pays.
服务范围覆盖大西洋中部至中西部、服务人口超过6700万的PJM互联有限责任公司(PJM Interconnection LLC)于周四晚间提交了该提案。此前,联邦能源监管委员会(FERC)称其原计划“存在深层缺陷”,并将拍卖推迟了五个月。
PJM Interconnection LLC, which serves more than 67 million people from the Mid-Atlantic to the Midwest, filed the proposal late Thursday after the Federal Energy Regulatory Commission called its original plan “deeply flawed” and delayed the auction by five months.
根据修订方案,PJM将根据2026年至2028年夏季预测峰值需求的增量来决定采购多少供电量。成本随后将按各公用事业分区在这一增量中所占份额进行分摊。
Under the revised plan, PJM would base the amount of supply it procures on the increase in forecast peak demand between 2026 and summer 2028. Costs would then be allocated according to each utility zone’s share of that growth.
此举涉及可能超过200亿美元的给付,用于新建天然气发电厂及其他电源,为Constellation Energy Corp.、NRG Energy Inc.、Vistra Corp.和Talen Energy Corp.等发电企业创造了重大机遇。
At stake are potentially more than $20 billion in payouts for new natural gas-fired plants and other sources, creating a significant opportunity for power producers such as Constellation Energy Corp., NRG Energy Inc., Vistra Corp. and Talen Energy Corp.
American Electric Power曾威胁退出PJM。根据该提案,任何退出的公用事业公司仍需承担为其辖区内数据中心需求服务所需发电机组的付款责任。PJM还希望取消某些市政公用事业公司和合作社的退出选择权。
American Electric Power has threatened leave PJM. Under the proposal, any utility that exits would remain responsible for payments to generators needed to serve data-center demand in its territory. PJM also wants to eliminate the ability of certain municipal utilities and cooperatives to opt out.
这个覆盖13个州的电网已拥有全美最大规模的数据中心集群,并因如何在不让居民和企业背负更高电费的前提下满足快速发展的AI行业需求,而陷入消费者、监管和政治层面的动荡。这份最新提交的文件将决定这些成本如何在客户间分摊,以及如果有公用事业公司退出市场,由谁承担责任。
The 13-state grid is already home to the nation’s largest concentration of data centers and has become embroiled in consumer, regulatory and political turmoil over how to meet the needs of the fast-moving AI industry without saddling households and businesses with higher power bills. This latest filing would determine how those costs are spread among customers and who remains liable if a utility leaves the market.
“分配方式正是美国联邦能源监管委员会(FERC)有所保留的地方,我仍然认为,修订后的方案虽然会招致批评,但很可能会获批,”经纪公司Tradition Energy研究总监加里·坎宁安表示。“值得注意的是,任何预期需求增长的公用事业的所有消费者都将为此买单,而不仅仅是新增负荷。”PJM正在修订需求预测。此前的预测显示,在考虑数据中心加速发展的因素之前,2028年夏季将出现6.8吉瓦的容量缺口。
“The allocation method was what FERC had reservations about, and I still think the revised leaves the door open to criticism but is likely to get approved,” said Gary Cunningham, director of research at brokerage Tradition Energy. “It is worth noting that all consumers in any utility where there is expected demand growth will pay, not just new load.”PJM is in the process of revising its demand forecasts. Earlier projections showed a 6.8-gigawatt capacity shortfall for summer 2028, before accounting for the accelerating pace of data-center development.
“最终,PJM在该计划下不会购买太多新增容量,所以这是雷声大雨点小,对可靠性的实际帮助不大,”坎宁安说。
“In the end, PJM isn’t going to buy much new capacity under the program so it is a lot of noise for not a lot of actual help for reliability,” Cunningham said.
如果FERC批准修订方案,这场名为“可靠性兜底采购”的拍卖将于3月1日至3月28日举行。PJM仍计划采购为期15年的供应,价格上限为每兆瓦日555美元,这将是创纪录的支出。PJM从未举行过此类拍卖。其下一次年度容量拍卖定于12月。
If FERC approves the revisions, the auction — dubbed the Reliability Backstop Procurement — would run from March 1 through March 28. PJM still aims to procure supplies for 15 years with price cap of $555 per megawatt-per day, which would be a record payout. PJM has never held an auction of this kind. Its next annual capacity auction is scheduled for December.
如果以该价格采购全部6.8吉瓦容量,每年向发电商的付款将接近14亿美元,即15年总计约207亿美元。
Procuring the full 6.8 gigawatts at that price would result in nearly $1.4 billion a year in payments to generators, or about $20.7 billion over the full 15 years.