卡尼推动管道项目快速审批面临原住民诉讼激增Carney’s Push to Fast-Track Pipeline Faces Mounting Indigenous Lawsuits

点「原文对照」整页切到原文,或双击某段只看那段的原文。

不列颠哥伦比亚省阿伯茨福德郊外一处堆放场内的管道部件。摄影:科尔·伯斯顿/法新社/盖蒂图片社Pieces of pipeline in a storage lot outside of Abbotsford, British Columbia. Photographer: Cole Burston/AFP/Getty Images

加拿大部长马克·卡尼面临一波法庭挑战,针对的是他利用其政府设计的一项法律机制,决定将一条管道项目列为快速通道建设的决定。

Minister Mark Carney faces a wave of court challenges to his decision to fast-track a pipeline project under a legal mechanism his government devised to speed up construction of major infrastructure.

九个原住民群体已请求法官审查并推翻加拿大政府10月1日作出的命令,该命令将一条拟建的从阿尔伯塔省通往西海岸的原油管道指定为“国家利益项目”,以加快其建设进程。

Nine Indigenous groups have requested that a judge review and overturn the Canadian government’s Oct. 1 order to designate a proposed crude oil pipeline from Alberta to the west coast as a “project of national interest” to accelerate its building.

根据周一发布的一份新闻稿,这些于10月30日新提交的诉讼来自不列颠哥伦比亚省的社区,包括奇姆第一民族、波士顿巴第一民族、下尼古拉印第安部落、夸特伦第一民族和察特利普第一民族。

The fresh claims filed Oct. 30 come from British Columbia communities including the Cheam First Nation, Boston Bar First Nation, Lower Nicola Indian Band, Kwantlen First Nation and Tsartlip First Nation, according to a Monday news release.

奇姆第一民族的诉讼被告为加拿大联邦政府和阿尔伯塔省政府。一份诉状指控卡尼内阁“在法律上犯错,在未进行充分协商的情况下推进”,并援引了加拿大宪法承认的权利。诉状还引用了加拿大对《联合国土著人民权利宣言》作出的承诺。

The Cheam’s claim is filed against Canada and Alberta. A filing alleges Carney’s cabinet “erred in law by proceeding without adequate consultation” with Indigenous groups, citing rights recognized in Canada’s constitution. It also cites Canada’s commitments to the United Nations Declaration on the Rights of Indigenous Peoples.

“不列颠哥伦比亚印第安酋长联盟主席、大酋长斯图尔特·菲利普在新闻发布会上表示:“我向企业传达的根本、基本信息是:在不列颠哥伦比亚省投资,买家自负,因为我们不会退让。”

“My fundamental, basic message to the corporations is: Buyers beware when you invest in British Columbia, because we’re not standing down,” Grand Chief Stewart Phillip, president of the Union of BC Indian Chiefs, said at a news conference.

新的挑战紧随冷湖第一民族于10月已提交的一起诉讼之后。该群体位于产油省份阿尔伯塔省。

The new challenges follow one already filed by the Cold Lake First Nations in October. That group is based in the oil-producing province of Alberta.

在不列颠哥伦比亚省本拿比,一艘油轮正在跨山输油管道系统终点的西岭海运码头装油。An oil tanker is loaded at the Westridge Marine Terminal at the end point of the Trans Mountain pipeline system in Burnaby, British Columbia.

该管道的“国家利益”地位源于卡尼政府去年通过的一项法律,这是其应对唐纳德·特朗普总统关税、旨在增长经济和实现贸易多元化战略的核心支柱。该法律允许政府根据项目“如何”推进来审查选定项目,而非审查项目“是否”应当推进。加拿大枢密院办公室的一名代表未立即回应置评请求。

The pipeline’s “national interest” status comes from a law passed by Carney’s government last year, a central pillar of its strategy to grow the economy and diversify trade in response to President Donald Trump’s tariffs. The law allows the government to review selected projects based on “how” they should proceed, versus “whether” they should. A representative for the government’s Privy Council Office didn’t immediately respond to a request for comment.

这条日输百万桶的输油管道被命名为“太平洋连线”,是根据卡尼的《建设加拿大法案》指定的首个项目,被视为实现加拿大出口多元化的关键。预计该管道将主要沿用现有跨山输油管道的路线,但终点将设在温哥华以南的一个新码头,该码头可容纳更大型的油轮。

The million-barrels-per-day oil pipeline, dubbed “Pacific Link,” was the first project to be designated under Carney’s Building Canada Act and is seen as key to diversifying Canadian exports. It’s largely expected to follow the route of the existing Trans Mountain pipeline, but end at a new terminal south of Vancouver that can accommodate larger oil tankers.

代表其中一个申请民族的律师杰西卡·克洛格表示,其中一起诉讼主张,如果法官认定根据《建设加拿大法案》无法实现“自由、事先且知情同意”,则他们还希望法院宣告该法律与《联合国土著人民权利宣言》(UNDRIP)不一致。

Jessica Clogg, a lawyer for one of the applicant nations, said one of the cases argues that if a judge finds that “free, prior and informed” consent is not possible under the Building Canada Act, then they also want a declaration that the law is inconsistent with UNDRIP.

不列颠哥伦比亚省原住民议会当选区域酋长特里·蒂吉表示:“我们面临一场真正的斗争。”他说,政府“在一年内完成一个审查”即批准项目的目标是“站不住脚的”。

“We have a real battle on our hands,” said Terry Teegee, the elected regional chief of the British Columbia Assembly of First Nations. The government’s objective of getting projects approved in “one year, one review” is “untenable,” he said.

他在给总理的信息中说:“我们不再是请求——我们是要求你们来到不列颠哥伦比亚省,出来与我们的酋长和领导层会面。”

“We’re not asking any more — we’re telling you to come out to British Columbia, come out and meet with our chiefs and our leadership,” he said in a message to the prime minister.

跨山输油管道的扩建项目也曾面临原住民的法律挑战,迫使联邦政府重做了部分原住民磋商工作。类似的法庭挑战也导致了恩布里奇公司拟建的通往不列颠哥伦比亚省北部海岸的“北部门户”输油管道项目被取消。

The expansion of the Trans Mountain pipeline also faced legal challenges from First Nations, forcing the federal government to redo part of its Indigenous consultations. Similar court challenges also contributed to the cancellation of Enbridge Inc.’s proposed Northern Gateway pipeline to BC’s north coast.