字号·· | 护眼
华尔街日报

AI公司争相应对一个对数据中心充满敌意的世界AI Companies Scramble to Navigate a World Hostile to Data Centers

点「原文对照」整页切到原文,或双击某段只看那段的原文。

去年得克萨斯州阿比林市正在建设的数据中心建筑。(谢尔比·陶伯/路透社)Data-center buildings under construction in Abilene, Texas, last year. (Shelby Tauber/Reuters)

周三中期选举的尘埃还未落定,OpenAI领导人就开始着手处理一个紧迫问题:选举结果是否会让公司更难获得维持增长所需的海量算力?

The dust from the midterms had hardly settled Wednesday when OpenAI leaders began reckoning with an urgent question: would the outcome make it harder to secure the vast amounts of computing power the company needs to keep growing?

知情人士透露,在一次员工问答环节中,OpenAI首席执行官山姆·奥尔特曼回答了关于数据中心和公众对AI看法的问题。前一天,一场数据中心反对浪潮帮助承诺冻结数据中心开发的候选人赢得了得克萨斯州、佐治亚州、俄亥俄州和密歇根州的州议会席位——这些州都是数据中心建设的主要州。

During a Q&A with employees, OpenAI Chief Executive Sam Altman fielded questions about data centers and public sentiment on AI, according to people familiar with the matter. A day earlier, a wave of data-center opposition had helped candidates promising to freeze development win statehouses in Texas, Georgia, Ohio and Michigan—all major states for data-center sites.

知情人士称,奥尔特曼承认公众担心用水问题,并表示无论出于何种原因,他都理解人们为何可能不想住在数据中心附近。他一度设想,公司或许应该考虑在沙漠建设数据中心。

Altman acknowledged that the public is concerned about water use and said that whatever the reason, he understood why people might not want to live near data centers, the people said. At one point, he mused that the company should perhaps look to build data centers in the desert.

《华尔街日报》此前报道,与此同时,高层领导人正忙于讨论公司明年是否需要重新设定数据中心容量预期。据该报查阅的信息显示,参与OpenAI数据中心开发的员工们正在交换关于关键州新当选民主党政客的情报,并讨论如何最好地与他们接触。

Meanwhile, senior leaders were busy discussing whether the company would need to reset expectations for its data-center capacity next year, The Wall Street Journal previously reported. And employees involved in OpenAI’s data-center development were exchanging intelligence on newly elected Democratic politicians in key states and discussing how best to engage with them, according to messages viewed by the Journal.

OpenAI首席执行官萨姆·奥特曼OpenAI CEO Sam Altman

硅谷各地也出现了类似场景:那些已向人工智能竞赛投入数千亿美元、并精心培养各级政府中AI友好官员关系的科技公司,纷纷加紧为新现实做计划。一夜之间,它们发现自己面临全面暂停建设、更严格的环境法规、更长的审查时间表,以及可能进一步拖累其进程的新AI安全法规的前景。

Across Silicon Valley, similar scenes played out as tech companies that have committed hundreds of billions of dollars to the artificial-intelligence race, and carefully cultivated relationships with AI-friendly officials at all levels of government, rushed to plan for a changed reality. Overnight, they found themselves facing the prospect of blanket moratoriums, tighter environmental regulations and longer review timelines, along with potential new AI-safety regulations that could further bog them down.

科技投资者布拉德·格斯特纳在“全押”播客节目中表示,明年计划在美国建设的数据中心中,多达35%现在面临风险。

The tech investor Brad Gerstner said on the “All-In” podcast that as much as 35% of the U.S. data-center construction planned for next year is now at risk.

负责政府关系的所谓“超大规模”公司高管迅速行动,与当选州长及其过渡团队建立沟通渠道,试图了解他们在竞选期间的言论将如何转化为政策行动。

Executives in charge of government relations for so-called hyperscaler companies moved quickly to open lines of communication with incoming governors and their transition teams, seeking an understanding of how their campaign-trail rhetoric would translate into policy actions.

Meta平台总裁迪娜·鲍威尔·麦考密克(凯特琳·塔克/尼基·里奇为《华尔街日报》拍摄)Dina Powell McCormick, president of Meta Platforms (Katelyn Tucker/Nikki Ritcher for WSJ)

Meta Platforms总裁、负责监督其AI基础设施运营的Dina Powell McCormick周三晚在《华尔街日报》科技大会上表示,公司已经发现一位当选州长愿意进行磋商。

Dina Powell McCormick, who as president of Meta Platforms oversees its AI-infrastructure operations, said at the WSJ Tech conference Wednesday night that the company had already found one incoming governor prepared to parley.

她说:“我们确实遇到一位昨晚获胜的州长,他在竞选纲领中把数据中心作为重点,他说:‘只要过完就职典礼,我们就见面,因为我们不想失去这笔在我们镇上的投资。我们不希望这些工作机会流向别处。’”但总体而言,Powell McCormick表示,Meta认为在美国建设数据中心“将会更难”,从零开始建成新数据中心将“极具挑战性”。

“We did have a governor that won last night who did make data centers a big part of their platform say, ‘As soon as we get past the inauguration, let’s meet, because we don’t want to lose this investment in our town. We don’t want these jobs to go elsewhere,’ ” she said. But on the whole, Powell McCormick said, Meta assumes that building data centers in the U.S. is “going to be harder” and getting new ones done from scratch will be “very challenging.”

她说,Meta和其他科技公司越来越多地考虑在美国境外建设新数据中心,作为绕过新障碍的一种途径。另一条路径是扩建现有数据中心,因为周边社区已从创造就业和税收收入中获益,不需要太多说服。

She said Meta and other tech companies are increasingly considering building new data centers outside the U.S. as one way around the new hurdles. Another avenue, she said, is to scale up existing data centers, where surrounding communities that have seen benefits in the form of job creation and tax revenue don’t require as much persuasion.

Powell McCormick表示,要想有任何希望赢得公众支持,AI行业必须在讲述其产品和潜在社会效益方面做得好得多。

To have any hope of winning over the public, Powell McCormick said, the AI industry will have to get much better at talking about its product and the potential societal benefits.

她说:“我认为我们必须加倍、甚至加倍再加倍地讲好这个故事。”

“I think we have to double and triple down on telling the story,” she said.

OpenAI总裁格雷格·布罗克曼同样在会议上发言,呼应了这一观点,他说:“我们需要更好地向当地社区真正传达,为什么数据中心对他们来说可能是有益的。”周四,OpenAI成为最新一家公布广泛承诺的AI巨头,规范其建设新数据中心的方式。该公司表示,不会要求公职人员签署保密协议即可参与数据中心谈判,并将征求社区意见,就其基础设施投资在能源、用水和噪音方面的影响提供清晰的公开信息。

OpenAI President Greg Brockman, also speaking at the conference, echoed that point, saying, “We need to do a better job of really communicating to local communities about why data centers are something that can be beneficial to them.”On Thursday, OpenAI became the latest AI giant to unveil a broad commitment governing how it approaches building new data centers. The company said it would not require public officials to sign nondisclosure agreements to engage in data-center negotiations and that it would solicit community input and provide clear public information about the energy, water and noise impacts of its infrastructure investments.

俄亥俄州新奥尔巴尼的一个Meta人工智能数据中心项目。A Meta AI data-center project in New Albany, Ohio.

Anthropic在上周为计划中的首次公开募股(IPO)提交的S-1文件中,向投资者预警了地方和州政府可能采取数据中心暂停令的风险。文件称:“此类暂停令或类似行动,可能会延迟或阻止我们赖以进行计算的设施的建设或扩建。”

Anthropic, in an S-1 filing last week for a planned initial public offering, previewed for investors the risk that local and state governments might adopt data-center moratoriums. “Such moratoriums, or similar actions, could delay or prevent the construction or expansion of facilities on which we depend for compute,” the filing said.

Anthropic表示,作为“降低在美国运营我们绝大部分计算基础设施所带来的集中风险”计划的一部分,公司正在多个“非美国司法管辖区”推进项目。S-1文件详细列出了截至2045年约8954亿美元的AI计算和基础设施承诺。该公司此前已单独宣布在得克萨斯州和纽约州建设数据中心的计划,相关场地预计将于今年投入使用。

Anthropic said it was pursuing projects in several “non-U.S. jurisdictions” as part of a plan to “reduce concentration risks associated with operating a significant portion of our compute infrastructure in the United States.”The S-1 detailed approximately $895.4 billion of AI computing and infrastructure commitments through 2045. The company has separately announced plans to build data centers in Texas and New York, with sites coming online this year.